Skip to Content
Search
None

Purple Line Extension - Section 3

The last section of the Purple Line Extension Transit Project, Section 3, will add 2.59 miles of new rail to Metro’s Rail system and connect downtown Los Angeles to the Westside. The two new stations will be added at Wilshire/Westwood and Wilshire/Veteran Administration property. Section 3 received the approval to move forward by Metro's board in 2016. Currently, in pre-construction, the project is anticipated to begin construction in 2019 and be open for operations in 2026.

Purple Line Extension, Section 3 Community Meetings

Metro holds regular meetings to update stakeholders on the project, view the community meeting presentations .

Purple Line Extension, Section 3 Pre-Construction Notices

View up to date pre-construction notices .


Insert main page content

Construction Notices

Start Date Notice Brief More Info
07/06/2018 Advanced Utility Relocation (AUR) on Wilshire Blvd. between Glendon Ave. & Gayley Ave.
Area: Wilshire/Glendon, Wilshire/Gayley

Metro contractors are continuing excavation work to relocate underground water, power and telecommunications equipment in Westwood. 

More information about Advanced Utility Relocation (AUR) on Wilshire Blvd. between Glendon Ave. & Gayley Ave. in HTML format
06/26/2018 Update: Advanced Utility Relocation (AUR) at Wilshire Blvd./Westwood Blvd.
Area: Wilshire/Westwood

Metro contractors are continuing excavation work to relocate underground water, power and telecommunications equipment in Westwood. AUR is expected to be completed in 2020. 

More information about Update: Advanced Utility Relocation (AUR) at Wilshire Blvd./Westwood Blvd. in HTML format

Insert main page content


Pre-Construction

2018

2017

2016


Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero