Purple Line Extension - Section 3

The last section of the Purple Line Extension Transit Project, Section 3, will add 2.56 miles of new rail to Metro’s Rail system and connect downtown Los Angeles to the Westside. The two new stations will be added at Wilshire/Westwood and Wilshire/Veteran Administration property. Section 3 received the approval to move forward by Metro's board in 2016. Currently, in pre-construction, the project is anticipated to begin construction in 2019 and be open for operations in 2026.

Purple Line Extension, Section 3 Community Meetings

Metro holds regular meetings to update stakeholders on the project, view the community meeting presentations .

Purple Line Extension, Section 3 Pre-Construction Notices

View up to date pre-construction notices .


Insert main page content

Construction Notices

Start Date Notice Brief More Info
11/19/2018 Purple Line Extension Community Meetings & Events
Area: Purple Line Extension

Purple Line Extension Transit Projects community meetings and events. 

More information about Purple Line Extension Community Meetings & Events in HTML format
11/09/2018 Advanced Utility Relocation (AUR) on Wilshire Blvd and Veteran Ave.
Area: Wilshire/Veteran

Equipment installation at Wilshire Blvd. and Veteran Ave., Wednesday, November 14, 9am to 3:30pm

More information about Advanced Utility Relocation (AUR) on Wilshire Blvd and Veteran Ave. in HTML format
10/29/2018 Westwood Advance Utility Relocation (AUR) Look-Ahead
Area: Westwood

Metro contractors are continuing excavation work to relocate underground water, power and telecommunications equipment in Westwood. AUR is expected to be completed in 2020. 

More information about Westwood Advance Utility Relocation (AUR) Look-Ahead in HTML format