Purple Line Extension - Section 2

The second section of the Purple Line Extension Transit Project includes 2.59 miles of additional tracks to Metro’s Rail system and two new stations at Wilshire/Rodeo and Century City/Constellation. The project received full Federal funding from the U.S. Department of Transportation in January 2017 and is now under construction. Construction for Section 2 is planned to begin in 2018. The extension is expected to begin operations by 2025 and will continue the Purple Line from Miracle Mile through Beverly Hills and into Century City.

Wilshire/Rodeo Station



The Wilshire/Rodeo station box will be located under Wilshire Bl from Beverly Dr to Canon Dr, with the station entrance on the southwest corner of Wilshire Bl and Reeves Dr. Located in the heart of Beverly Hills, the station will not only service those who live and work in the area, but also visitors seeking to shop and dine in the Golden Triangle Area.

Century City/Constellation Station

 Century City/Constellation Station

The Century City/Constellation station box will be located under Constellation Bl between Century Park East and Solar Way (between Avenue for the Stars and Century Park West), with a station entrance at the northeast corner of Constellation Bl and Avenue of the Stars. Situated in the center of one of the county’s biggest job hubs, it is anticipated that thousands will board and alight during their daily commute.

Purple Line Extension, Section 2 Pre-Construction Notices

View up to date construction notices .

Purple Line Extension, Section 2 Community Meetings

Metro holds regular meetings to update stakeholders on the project,  view the community meeting presentations .


Insert main page content

Construction Notices

Start Date Notice Brief More Info
07/19/2018 Nighttime Advance Utility Relocation Work on Constellation Blvd. and Avenue of the Stars
Area: Constellation/Avenue of the Stars

Advanced utility relocation (AUR) for Department of Water and Power (DWP) and AT&T will continue in Century City along Constellation Blvd. on the west side of Avenue of the Stars. 

More information about Nighttime Advance Utility Relocation Work on Constellation Blvd. and Avenue of the Stars in HTML format
07/13/2018 Update: Seismic Boring Study on Wilshire Blvd.
Area: Wilshire/Peck, Wilshire/Bedford, Wilshire/McCarty, Wilshire/Roxbury, Wilshire/Reeves, Wilshire/Canon, Wilshire/Camden, Wilshire/Rodeo

The seismic boring study in the City of Beverly Hills for Section 2 of the Purple Line Extension Project continues throughout the month of July.

More information about Update: Seismic Boring Study on Wilshire Blvd. in HTML format
07/13/2018 Update: K-rail Set Up for Advanced Utility Relocation on Wilshire Blvd. in Beverly Hills
Area: Wilshire/Crescent, Wilshire/Beverly

Pre-construction activity includes advanced relocation of utility lines prior to station construction. SoCal Gas (SCG) and AT&T will work within the same work zone with the same traffic control measures. This requires K-rail set up on Wilshire Blvd., between Crescent Dr., and Beverly Dr.

More information about Update: K-rail Set Up for Advanced Utility Relocation on Wilshire Blvd. in Beverly Hills in HTML format
07/11/2018 Demolition of 9430 Wilshire Blvd. (former Ace Gallery Building)
Area: Wilshire/Beverly, Wilshire/Reeves

The design-build contractor for the Purple Line Extension project in Section 2 continues pre-construction work activities in Beverly Hills to prepare the construction staging area located at the former Ace Gallery Building at 9430 Wilshire Blvd.

More information about Demolition of 9430 Wilshire Blvd. (former Ace Gallery Building) in HTML format
07/09/2018 CCTV of Existing Utilities & Pavement Deflection Testing
Area: Wilshire/El Camino, Wilshire/Crescent

Pre-construction includes Pavement Deflection Testing to evaluate the existing pavement to design pavement reconstruction of the streets. No additional traffic control measures will be needed for this work.

More information about CCTV of Existing Utilities & Pavement Deflection Testing in HTML format
06/29/2018 Century City: Monthly Look-Ahead - July 2018
Area: Century City

This monthly notification is an outline of construction activities in Century City for the month of July 2018.

More information about Century City: Monthly Look-Ahead - July 2018 in HTML format
06/29/2018 Constellation Blvd. Closure
Area: Constellation/Century Park East

Constellation Bl at Century Park East will be closed for approximately 15 months to construct a launch box for the Purple Line Extension tunnel boring machines digging the twin tunnels for the underground subway through Century City.

More information about Constellation Blvd. Closure in HTML format
05/17/2018 Advance Utility Relocation on Constellation Blvd. East of Avenue of the Stars
Area: Constellation/Avenue of the Stars

Advanced utility relocation (AUR) for LADWP will continue in Century City along Constellation Blvd. east of Avenue of the Stars at Century Park East starting Friday, May 18 through Friday, May 25 from 7pm to 6am. There will be no work on Saturday, May 19.

More information about Advance Utility Relocation on Constellation Blvd. East of Avenue of the Stars in HTML format
05/01/2018 K-rail set up for Advanced Utility Relocation on the south side of Wilshire Blvd.
Area: Wilshire/Crescent, Wilshire/Reeves

K-rail will be set up on Tuesday, May 29, 2018 and will be in place through July 2018.

More information about K-rail set up for Advanced Utility Relocation on the south side of Wilshire Blvd. in HTML format
01/10/2018 Reubicación de la parada de autobus - Wilshire/Rodeo
Segment: Wilshire
Area: Wilshire/Rodeo

A partir del domingo 14 de enero, las paradas de autobús de la línea 720 del autobús de tránsito rápido, la línea 20 local del Metro y la línea 786 de Antelope Valley (ATVA) se reubicarán.

More information about Reubicación de la parada de autobus - Wilshire/Rodeo in HTML format
01/10/2018 Bus Stop Relocations - Wilshire/Rodeo
Segment: Wilshire
Area: Wilshire/Rodeo

Beginning Sunday, January 14, bus stops for Metro Rapid Bus 720, Metro Local 20, and Antelope Valley (ATVA) 786 will be relocated. Bus stops are being relocated due to on-going construction activities on Wilshire Blvd.  

More information about Bus Stop Relocations - Wilshire/Rodeo in HTML format


Meeting Presentations

2018

2017

2016


Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero