Where We Are in the Process
In 2007, Metro initiated an Alternatives Analysis (AA) Study which identified and analyzed 33 routes for the Regional Connector. After technical analysis and extensive community input, the study yielded two "build" alternatives which utilize Light Rail Transit (LRT) technology as well as two required alternatives, the No-Build and Transportation System Management alternatives.
In early 2009, these four alternatives were authorized by the Metro Board of Directors for further study in the next phase, the Draft Environmental Impact Statement/Report (Draft EIS/EIR). During this environmental phase, the Metro Board added a fifth alternative in response to community input. The alternatives currently under analysis in the Draft EIS/EIR include the following alternatives:
- Fully Underground LRT
- At-Grade Emphasis LRT
- Underground Emphasis LRT
- No-Build
- Transportation System Management (TSM)
During the Draft EIS/EIR process, Metro will further refine the project alternatives (including alignments and station locations), assess the potential impacts of the alternatives and address possible mitigation measures. We will also consider the cost effectiveness of the alternatives as well as funding options for constructing the project.
At the conclusion of the Draft EIS/EIR process in late 2010, the Metro Board will recommend a Locally Preferred Alternative (LPA) which will identify the project to move forward into the Final EIS/EIR process. Metro and the Federal Transit Administration (FTA) will be preparing a joint document that meets the requirements of both the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA).
| Summary of Environmental Process |
| Date |
Milestone |
| 2007 |
October: Alternatives Analysis Study initiated & Early Scoping Meetings completed |
| 2008 |
February: Community Update Meetings held October: Public Hearings for Alternatives Analysis phase completed |
| 2009 |
January: Alternatives Analysis approved by Metro Board of Directors & Draft EIS/EIR initiated March/April: Scoping Meetings held June: Urban Design Working Group meetings initiated September: Little Tokyo Working Group meetings began November: Community Update Meetings held Winter: Additional Build Alternative added |
| 2010 |
Draft EIS/EIR continues Little Tokyo Working Group meetings ongoing April: Community Update Meetings held Anticipated: August: Release of Draft EIS/EIR September: Public Hearings scheduled to receive formal comment November: Metro Board of Director Meeting
- Identify Locally Preferred Alternative (LPA)
- Identify Candidate Mitigation Measures
Winter: Begin Preliminary Engineering |
| 2011 |
Anticipated: Completion of Final EIS/EIR Public Hearings Metro Board of Director Meeting –LPA Recommended for Adoption –Mitigation Monitoring Program Adopted |
| 2012 - 2013 |
Anticipated: Stakeholder Meetings Final Design |
| 2014 – 2019 |
Anticipated: Construction |
| 2019 |
Anticipated: Regional Connector Opens |
Keywords: Regional Connector Transit Corridor
Last Revised:
Wednesday June 09, 2010 5:24:25 PM
Printer Friendly Version for '
The Process '