|
|
|
|
|
|
|
|
Home > Projects & Programs > I-405 Sepulveda Pass Improvements Project
![]() |
![]() |
![]() |
![]() |
The latest schedule for completing the I-405 Sepulveda Pass Improvements Project cites mid-2014 as the completion date. It is likely that the Wilshire Segment will open first, followed by the Mulholland Segment.
Because of the complex work remaining in the Sunset Segment (that segment runs from Constitution Av to the Getty Center ramps), we anticipate the Sunset Segment will be the last segment completed.
Here are our key milestones to reach for the remainder of 2013.
Key Milestones
| Project Component | Complete (%) |
|---|---|
| Bridges | 100 |
| On- and off-ramps | 90 |
| Retaining and sound walls | 83 |
| underpasses and structures | 90 |
| Utilities | 100 |
| Wilshire ramps | 100 |
The I-405 Sepulveda Pass Improvements Project will add a 10-mile HOV lane and improve supporting infrastructure such as ramps, bridges and sound walls on the San Diego Fwy. (I-405); while widening lanes from the Santa Monica Fwy. (I-10) to the Ventura Fwy. (US-101).
This project will reduce existing and forecasted traffic congestion on the I-405 and enhance traffic operations by adding freeway capacity in an area that experiences heavy congestion. In addition to these modifications, the project will improve both existing and future mobility and enhance safety throughout the corridor.
Project benefits include a decrease in commuter time, reduction in air pollution, and promotion of ridesharing.
The I-405 Sepulveda Pass Improvements Project will:
Construction Notice Archives | Lane Closures | Detour Maps
Get construction updates on Twitter
| Start Date | Notice Brief | More Info |
|---|---|---|
|
05/24/2013 |
Segment: Wilshire A full night closure of Sepulveda Bl from Ohio Av to Wilshire Bl is scheduled for Friday, May 24, 2013 from 10pm to 10am. This closure is necessary to remove falsework for the northbound I-405 off-ramp to eastbound Wilshire Bl. Click here for Freeway Closures |
|
|
05/21/2013 |
Segment: Wilshire Construction on the northbound I-405 on-ramp from Santa Monica Bl is scheduled to continue through June 11. To address congestion surrounding the area, particularly congestion at the merge points, the northbound I-405 Santa Monica Bl on-ramp will be temporarily reconfigured. This reconfiguration, scheduled to be complete by May 28, will add an additional merge lane and provide 1,000 feet of merging space for the Santa Monica Bl on-ramp and Wilshire off-ramp traffic. This reconfiguration is scheduled to be in effect for approximately three weeks. Click here for Freeway Closures |
|
|
05/16/2013 |
Segment: Wilshire The bicycle path on the west side of the southbound I-405 freeway from Waterford St to Constitution Av will be closed from through Thursday, May 16, 2013, from 7am to 3:30pm and from 10pm to 7am. The closure is necessary for construction of the sound wall along the southbound I-405 from Waterford St to Constitution Av. Click here for Freeway Closures |
|
|
05/10/2013 |
Segment: Wilshire Full 10-hour northbound freeway closures from the Santa Monica Bl off-ramp to the Santa Monica Bl on-ramp are scheduled for the nights of Friday, May 10, Friday, May 17, and Saturday, May 18, 2013 from 11pm to 9am. The full northbound freeway closures at Santa Monica Bl are scheduled to facilitate the approach slab repair (the connection between the freeway and the freeway bridge). Click here for Freeway Closures |
|
|
04/26/2013 |
Segment: Mulholland Multiple closures during the April 26 weekend in the Mulholland Dr/Skirball Center Dr area include lane closures. For example, there will be lane closures and a flagging operation on Skirball Center Dr and the northbound Skirball Center Dr ramps from Friday, April, 26, at 10 pm, to Sunday, April 28, at 8 am. Both northbound Skirball Center Dr on- and off- ramps will be closed from Friday, April 26 to Sunday, April 28, 7pm to 8am. The Mulholland Bridge will be closed on Friday and Saturday night starting at 10 pm and ending at 8 am. Click here for Freeway Closures |
|
|
04/22/2013 |
Segment: Wilshire Westbound and eastbound Wilshire Bl from Sepulveda Bl to Bonsall Av will be closed Monday, April 22, 2013 and Tuesday, April 23, 2013 from 10pm to 5am. This closure is necessary to complete barrier work for the southbound I-405 off-ramp to eastbound Wilshire Bl. Click here for Freeway Closures |
|
|
04/22/2013 |
Segment: Wilshire |
|
|
04/20/2013 |
Segment: Wilshire A full closure of Wilshire Bl, from Sepulveda Bl to the southbound I-405 on- and off-ramps, is scheduled for Saturday, April 20, 2013 from 9pm to 6am. Click here for Freeway Closures |
|
|
04/18/2013 |
Segment: Wilshire A full nighttime closure of Sepulveda Bl from Ohio Av to Wilshire Bl is scheduled for Thursday, April 18, 2013 and Friday, April 19, 2013, 9pm to 6am. This closure is necessary to pour cement for the northbound I-405 off-ramp to eastbound Wilshire Bl. Click here for Freeway Closures |
|
|
04/12/2013 |
Segment: Sunset A full directional northbound freeway closure from the I-10 connector to the Olympic Bl on-ramp is scheduled for the nights of Friday, April 12, Saturday, April 13, and Sunday, April 14, 2013. The full northbound freeway closure is scheduled to prepare roadway and to stage K-rail for additional lane and median construction. |
|
|
04/09/2013 |
Segment: Wilshire A full closure of Sepulveda Bl from Ohio Av to Wilshire Bl is scheduled for Tuesday, April 9, 2013, from 9pm to 6am. This closure is necessary to pour cement for the northbound I-405 off-ramp to eastbound Wilshire Bl. Click here for Freeway Closures |
|
|
04/01/2013 |
Segment: Mulholland |
|
|
04/01/2013 |
Segment: Mulholland |
|
|
03/25/2013 |
Segment: Wilshire Westbound and eastbound Wilshire Bl from Sepulveda Bl to the southbound I-405 on and off-ramps will be closed Monday, March 25, from 10pm to 6am. This closure is necessary to pour cement for the southbound I-405 off-ramp to eastbound Wilshire Bl Bridge. Click here for Freeway Closures |
|
|
03/25/2013 |
Segment: Wilshire Effective Monday, March 25, 2013 through Wednesday, April 10, 2013, from 10pm to 6am, nightly lane reductions, street and ramp closures will be implemented at the northbound I-405 connector to eastbound and westbound I-10, as well as Pico Bl. This closure is necessary to remove deck plywood and demolish the existing Exposition Bl undercrossing. Click here for Freeway Closures |
|
|
03/25/2013 |
Segment: Wilshire Construction work on the Best Management Practices (BMP) at Cotner Av from Mississippi Av to La Grange Av begins Monday, March 25, 2013 through April 19, 2013 from 7am to 4pm. The work includes potholing, excavation and backfilling the infiltration structure for the BMP. Click here for Freeway Closures |
|
|
03/23/2013 |
Segment: Mulholland The contractor is scheduled to implement a full directional (northbound) freeway closure on the night of Saturday, March 23, 2013, from the Getty Center Dr ramps to US 101 freeway. Freeway lanes will begin to close as early as 11pm, leading up to the full northbound freeway closure from 1 am to 6 am, weather permitting. Click here for Freeway Closures |
|
|
03/17/2013 |
Segment: Wilshire Construction-related closures and lane reductions are scheduled to end Sunday, March 17, 2013, at 4am in preparation for the LA Marathon. No closures will occur after 4am for the I-405 Sepulveda Pass Improvements Project from the I-10 connector to I-405 to Montana Av, Sunday, March 17, 2013. Click here for Freeway Closures |
|
|
03/14/2013 |
Segment: Sunset Upcoming full nighttime closure and daytime lane reduction on Sepulveda Bl, from Montana Av to Moraga Dr ramps, and on Church Ln/Ovada Pl, from 300 ft west of Sepulveda Bl to Acanto St, begin on Thursday, March 14, 2013, and continuing until Wednesday, March 20, 2013. These closures and lane reductions are necessary to grind the existing roadway, pave and re-stripe Sepulveda Bl and Church Ln/Ovada Pl, as well as conduct bridge demolition and utility work. Click here for Freeway Closures |
|
|
03/13/2013 |
Segment: Wilshire Effective Wednesday, March 13, 2013 through Sunday, March 31, 2013, lane reductions and full-ramp closures will be implemented at southbound I-405 from the Olympic/Pico off-ramp to the eastbound and westbound I-10 connector. This closure is necessary to backfill, drill, set and install a retaining wall Click here for Freeway Closures |
|
|
03/13/2013 |
Segment: Wilshire Southbound Sepulveda Bl at Constitution Av will be reduced to one lane, Wednesday, March 13, 2013 through Friday, March 15, 2013, between 9am and 3pm. One lane will remain open on southbound Sepulveda Bl at Constitution Av. Flaggers will be present to assist with access. This closure is necessary to complete traffic signal reconfiguration at Sepulveda Bl and Constitution Av. Click here for Freeway Closures |
|
|
03/11/2013 |
Segment: Wilshire Construction at Beloit Av between Santa Monica Bl and Iowa Av, Monday, March 11, 2013 through Friday, March 15, 2013, between 6am and 5pm. Access will be maintained for pedestrians and vehicles on Beloit Av. This work is necessary to form, pour and strip the Santa Monica Bl on-ramp. Click here for Freeway Closures |
|
|
03/09/2013 |
Segment: Mulholland The contractor is scheduled to implement another full directional southbound freeway closure during the late night hours of Saturday, March 9, 2013, in order to construct falsework structures for the Mulholland Bridge. The directional full freeway closure will be from US 101 to the Getty Center Dr. ramps, weather permitting. Click here for Freeway Closures |
|
|
03/08/2013 |
Segment: Wilshire The Cotner Av on-ramp to northbound I-405 will be closed nightly, until Monday, March 11, 2013. During daytime hours, the on-ramp will be reduced from two lanes to one lane. Turn pockets on Cotner Av for on-ramp access will be closed nightly during the ramp closure. This closure is necessary to demolish the existing on-ramp, to conduct roadway paving and to shift K-rail for the new on-ramp. Click here for Freeway Closures |
|
|
03/08/2013 |
Segment: Wilshire The southbound I-405 off-ramp to westbound Wilshire Bl will be closed beginning Friday, March 8, 2013 at 8pm until 6am on Friday, March 22, 2013. This closure is necessary to demolish the existing off-ramp and to conduct roadway paving and K-rail shifts for the new off-ramp. Click here for Freeway Closures |
|
|
03/05/2013 |
Segment: Mulholland The contractor is anticipating to implement a full closure of Sepulveda Bl, between the southbound Getty ramps and northbound Getty on-ramp, beginning Tuesday, March 5, 2013, for approximately three nights. Click here for Freeway Closures |
|
|
03/05/2013 |
Segment: Wilshire The northbound Sepulveda Bl between Ohio Av and Wilshire Bl will be reduced to one lane Tuesday, March 5, 2013 through Monday, March 11, 2013, weekdays only, between 9am and 3:30pm. One lane will remain open on northbound Sepulveda Bl from Ohio Av to Wilshire Bl. This closure is necessary to complete pile driving and foundation support for the northbound I-405 on-ramp from eastbound Wilshire. Click here for Freeway Closures |
|
|
03/01/2013 |
Segment: Sunset The northbound I-405 will be reduced from 5 lanes to 2 lanes, from the Montana Av off-ramp to the Getty Center Dr off-ramp, for 55 hours, starting 10pm on Friday, March 1, 2013. The lanes will re-open at 5am on Monday, March 4, 2013. This lane reduction is necessary for paving of the future high occupancy vehicle (HOV) lane and for realignment of the I-405. Click here for Freeway Closures |
|
|
02/22/2013 |
Segment: Mulholland The contractor anticipates the closure of the northbound Skirball Center Drive on- and off-ramps during the February 22 - 24 weekend to support work toward the realignment of the northbound Skirball ramps. The ramps closure will begin at 7pm, Friday night, and last until 6am, Monday morning, weather permitting. Click here for Freeway Closures |
|
|
02/21/2013 |
Segment: Wilshire Wilshire Bl will be fully closed on week nights from Thursday, February 21, 2013 through Friday, March 1, 2013, from 10pm to 5am, from Bonsall Av to Sepulveda Bl. This night closure is necessary to install the overhang falsework for the I-405 Bridge at Wilshire Bl. Click here for Freeway Closures |
|
|
02/20/2013 |
Segment: Wilshire Pico Bl will be fully closed the nights of Wednesday, February 20, 2013 and Thursday, February 21, 2013, from 9pm to 6am, from Sawtelle Bl to Cotner Av. This night closure is necessary to form and pour the barrier and strip the forms for the I-405 Bridge at Pico Bl. Click here for Freeway Closures |
|
|
02/12/2013 |
Segment: Mulholland The contractor will implement nightly full closures of Sepulveda Bl between Skirball Center Dr and Mountaingate Dr from 10pm to 6am for approximately three months. These closures are anticipated to begin Tuesday, February 12, 2013. This closure is required to support the widening of Sepulveda Bl and create additional capacity to accommodate the new southbound Skirball ramps. Click here for Freeway Closures |
|
|
02/08/2013 |
Segment: Wilshire This is a revised notice. The Cotner Av on-ramp to northbound I-405 will be closed nightly, beginning Friday, February 8, 2013, until Friday, March 1, 2013. During daytime hours, the on-ramp will be reduced from two lanes to one lane. Turn pockets on Cotner Av for on-ramp access will be closed nightly during the ramp closure. This closure is necessary to demolish the existing on-ramp, and to conduct roadway paving and K-rail shifts for the new on-ramp. Click here for Freeway Closures |
|
|
01/18/2013 |
Segment: Sunset Steel pile driving will be conducted at the northbound I-405 Sunset Bl off-ramp from 7am to 4pm starting Friday, January 18, 2013. This work is expected to continue until Monday, February 4, 2013. The steel pile driving is necessary for construction of the bridge abutment foundation. Click here for Freeway Closures |
|
|
01/17/2013 |
Segment: Wilshire Wilshire Bl will be fully closed on week nights from Thursday, January 17, 2013, to Friday, February 8, 2013, from 10pm to 5am, from Federal Av to Sepulveda Bl. This night closure is necessary to install metal bridge decking for the southbound I-405 off-ramp to eastbound Wilshire Bl. Click here for Freeway Closures |
|
|
01/17/2013 |
Segment: Wilshire This is a revision to a prior notice. Wilshire Bl will now be fully closed on weeknights from Thursday, January 17, 2013,until Tuesday, February 12, 2013, from 10pm to 5am, from Federal Av to Sepulveda Bl. One weekend night closure is expected on Saturday, February 9, 2013. These night closures are necessary to install metal bridge decking for the southbound I-405 off-ramp to eastbound Wilshire Bl. Click here for Freeway Closures |
|
|
01/17/2013 |
Segment: Sunset The Sunset Way cul-de-sac will be closed from 7am to 5pm starting Thursday, January 17, 2013. The closure is expected to continue until Friday, January 25, 2013. This closure is necessary to excavate for construction of retaining wall 1738A Click here for Freeway Closures |
|
|
01/07/2013 |
Segment: Wilshire Exposition Bl will be fully closed on Monday, January 7, 2013, and Wednesday, January 9, 2013, 10pm to 5am, from Sawtelle Bl to Sepulveda Bl. This night closure is necessary to construct deck enforcement formwork for the I-405 Exposition Bl Bridge undercrossing. Click here for Freeway Closures |
|
|
12/03/2012 |
Segment: Sunset Construction of catch basins, manholes and storm drain lines will start at the intersection of Sepulveda Bl and Sepulveda Wy on Monday, December 3, 2012, for two weeks. Click here for Freeway Closures |
If Daily Closures are not displaying below, please visit the project Facebook or Twitter pages for the latest closures. |
The I-405 Sepulveda Pass Improvements Project utilizes Twitter to post closure updates every workday afternoon. For your convenience, the updates are organized by segment. You can also view these Daily Updates on our Facebook, Twitter.
Closure Widget: Learn how to embed the Daily Closures onto your website
More Info: Typical Freeway Closures | Service Delays | Detour Maps
| The abbreviations below help us organize the Daily Updates by segment. | ||||
|---|---|---|---|---|
|
Sunday Monday Tuesday Wednesday Thursday Friday Saturday |
SU MO TU WE TH FR SA |
All Wilshire Sunset Mulholland |
ALL WIL SUN MUL |
|
| Today's Closures | Date Posted | |
|---|---|---|
|
WE-ALL: Unless noted below, AM closures occur from 9am to 2:30pm. |
May 21st |
|
|
TU-ALL: Significant multiple cancellations of work in the Wilshire Segment tonight, including closure of northbound lanes. |
May 21st |
| Today's Closures | Date Posted | |
|---|---|---|
|
WE-WIL: Sepulveda Bl reduced to one lane each direction near Constitution Av. |
May 21st |
|
|
WE-WIL: Constitution bicycle path closed from Church Ln to Constitution, 7am to 5:30pm. |
May 21st |
|
|
TU-WIL: Southbound 2,3,4,5 lanes closed from Valley Vista to southbound Skirball off-ramp tonight, 1 to 4am. |
May 21st |
|
|
TU-WIL: Southbound 3,4,5 lanes closed from Valley Vista to southbound Skirball off-ramp tonight, 11pm to 4am. |
May 21st |
|
|
TU-WIL: Southbound 4,5 lanes closed from Valley Vista to southbound Skirball off-ramp tonight, 10pm to 4am. |
May 21st |
|
|
TU-WIL: Reduction of Sepulveda Bl to one lane each direction from Wilshire to north of Ohio cancelled for tonight. |
May 21st |
|
|
TU-WIL: Closure of southbound off-ramp to Santa Monica Bl cancelled for tonight. |
May 21st |
|
|
TU-WIL: Closure of northbound on-ramp from westbound Wilshire Bl cancelled for tonight. |
May 21st |
|
|
TU-WIL: Closure of northbound 4,5 lanes from Olympic Bl to north of Wilshire Bl cancelled for tonight. |
May 21st |
|
|
TU-WIL: Closure of northbound 5,6 lanes from I-10 to Olympic Bl cancelled for tonight. |
May 21st |
|
|
TU-WIL: Closure of northbound lanes from I-10 to Santa Monica Bl cancelled for tonight. |
May 21st |
|
|
TU-WIL: Northbound 1 lane closed from I-10 to Olympic Bl tonight, 11pm to 4am. |
May 21st |
|
|
TU-WIL: Closure of eastbound I-10 connector to northbound I-405 cancelled for tonight. |
May 21st |
|
|
TU-WIL: Closure of westbound I-10 connector to northbound I-405 cancelled for tonight. |
May 21st |
|
|
TU-WIL: Southbound HOV/1 lane closed from Pico to National tonight, midnight to 4am. |
May 21st |
|
|
TU-WIL: Southbound HOV lane closed from Pico to National tonight, 9pm to 4am. |
May 21st |
|
|
TU-WIL: Southbound on-ramp from westbound Wilshire Bl closed tonight, 11pm to 5am. |
May 21st |
|
|
TU-WIL: Southbound off-ramp to eastbound Wilshire Bl closed tonight, 9pm to 4am. |
May 21st |
|
|
TU-WIL: Southbound on-ramp from Santa Monica closed tonight, 10pm to 5am. |
May 21st |
|
|
TU-WIL: Southbound off-ramp to Olympic Bl closed tonight, 10pm to 5am. |
May 21st |
|
|
TU-WIL: Eastbound I-10 connector to southbound I-405 closed tonight, 10pm to 5am. |
May 21st |
|
|
TU-WIL: Northbound on-ramp from eastbound Wilshire Bl closed tonight, 8pm to 5am. |
May 21st |
|
|
TU-WIL: Northbound off-ramp to westbound Wilshire Bl closed tonight, 9pm to 5am. |
May 21st |
|
|
TU-WIL: Northbound 5, 6 lanes closed from I-10 to Olympic Bl tonight, midnight to 4am. |
May 21st |
|
|
TU-WIL: Northbound on-ramp from Santa Monica closed tonight, 8pm to 5am. |
May 21st |
|
|
TU-WIL: Northbound on-ramp from Olympic Bl closed tonight, 10pm to 5am. |
May 21st |
|
|
TU-WIL: Northbound 1 lane closed from 1-10 to Olympic, 11pm to 4am. |
May 21st |
| Today's Closures | Date Posted | |
|---|---|---|
|
WE-SUN: Sepulveda Bl northbound 2 lane closed from Church Ln to Montana Av. |
May 21st |
|
|
WE-SUN: Sunset Wy cul-de-sac closed at Sunset Bl, 5am to 2:30pm. |
May 21st |
|
|
WE-SUN: Sunset Bl westbound 2 lane closed near Thurston. |
May 21st |
|
|
WE-SUN: Sepulveda Bl southbound 2 lane closed from Moraga Dr to Montana Av. |
May 21st |
|
|
WE-SUN: Church Ln northbound 2 lane closed near Sepulveda Bl. |
May 21st |
|
|
TU-SUN: Southbound HOV, 1, 2 lanes closed near Sunset Bl tonight, 11pm to 4am. |
May 21st |
|
|
TU-SUN: Southbound HOV, 1 lane closed from Getty on-ramp to south of Sunset Bl tonight, 10pm to 4am. |
May 21st |
|
|
TU-SUN: Southbound HOV lane closed from Getty off-ramp to south of Sunset Bl tonight, 7pm to 5am. |
May 21st |
|
|
TU-SUN: Northbound 1, 2, 3 lanes closed from Sunset to Getty on-ramp tonight, 11pm to 5am. |
May 21st |
|
|
TU-SUN: Northbound 1 lane closed from Sunset Bl to Getty on-ramp tonight, 10pm to 6am. |
May 21st |
|
|
TU-SUN: Northbound on-ramp from Sunset closed 7pm to 5am. |
May 21st |
|
|
TU-SUN: Northbound off-ramp to Sunset closed 7pm to 5am. |
May 21st |
|
|
TU-SUN: Northbound off-ramp to Montana partially closed 7pm to 5am. |
May 21st |
| Today's Closures | Date Posted | |
|---|---|---|
|
WE-MUL: Northbound off-ramp to and on-ramp from Skirball Center Dr closed. |
May 21st |
|
|
WE-MUL: Southbound Valley Vista on-ramp closed 10am to 2:30pm. |
May 21st |
|
|
TU-MUL: Southbound off-ramp to Valley Vista closed tonight, 9pm to 5am. |
May 21st |
|
|
TU-MUL: Southbound US 101 connector to southbound I-405 closed tonight, 11pm to 4am. |
May 21st |
|
|
TU-MUL: Southbound 5 lane closed from Valley Vista to southbound Skirball off-ramp tonight, 7pm to 5am. |
May 21st |
|
|
TU-MUL: Closure of southbound off-ramp to Skirball Center Dr cancelled for tonight. |
May 21st |
|
|
TU-MUL: Southbound off-ramp to Valley Vista closed tonight, 7pm to 5am. |
May 21st |
|
|
TU-MUL: Southbound 5 lane closed from Valley Vista to Skirball tonight, 7pm to 5am. |
May 21st |
|
|
TU-MUL: Southbound on-ramp from Valley Vista closed tonight, 7pm to 5am. |
May 21st |
|
|
TU-MUL: Southbound off-ramp to Ventura closed tonight, 7pm to 5am. |
May 21st |
|
|
TU-MUL: Southbound 2, 3, 4, 5 lanes closed from Valley Vista to southbound Skirball off-ramp tonight, 1am to 3am. |
May 21st |
|
|
TU-MUL: Southbound 3, 4, 5 lanes closed from Valley Vista to southbound Skirball off-ramp tonight, 11pm to 4am. |
May 21st |
|
|
TU-MUL: Southbound 4, 5 lanes closed from Valley Vista to southbound Skirball off-ramp tonight, 10pm to 4am. |
May 21st |
|
|
TU-MUL: Southbound 5 lane closed from Valley Vista to southbound Skirball off-ramp tonight, 7pm to 5am. |
May 21st |
|
|
TU-MUL: Southbound on-ramp from Getty closed tonight, 7pm to 5am. |
May 21st |
|
|
TU-MUL: Southbound US I-101 connector to southbound I-405 closed tonight, 11pm to 4am. |
May 21st |
|
|
TU-MUL: Northbound on-ramp/auxiliary lane closed from Skirball to south of Ventura 7pm to 5am. |
May 21st |
|
|
TU-MUL: Northbound off-ramp to and on-ramp from Skirball Center Dr closed 7pm to 5am. |
May 21st |
|
|
TU-MUL: Fiume Walk fully closed from Sherman Oaks to Sepulveda tonight, 9pm to 5am. |
May 21st |
|
|
TU-MUL: Mulholland fully closed from Zeldins to Skirball tonight, 10pm to 5am. |
May 21st |
Construction Relations Team:
Kasey Shuda - Manager, Construction Relations
Tel: 310.846.3563
Erika Estrada - Sunset Segment (Constitution Av to Sepulveda Bl)
Tel: 310.846.2400
Megan Nangle - Wilshire Segment (National Bl to Constitution Av)
Tel:310.846.2400
Ron Macias - Mulholland Segment (Sepulveda B. to Ventura Bl)
Tel: 310.846.3564
Ned Racine - New Media
Tel: 310.846.3569
Yvette ZR Rapose - Director of Construction Relations
Tel: 213.922.2297
Contact Information:
Metro Community Relations
6060 Center Dr., 2nd Flr.
Los Angeles, CA 90045-2952
Tel: 213.922.3665
I405@metro.net
Sign up for our email list
For viewing MS Word, Powerpoint, and Excel documents - Download Adobe Acrobat Reader (free) or use Google Docs Reader (online)









