|
|
|
|
|
|
|
|
|
|
|
Home > Projects & Programs > I-405 Sepulveda Pass Improvements Project
The I-405 Sepulveda Pass Improvements Project will add a 10-mile HOV lane and improve supporting infrastructure such as ramps, bridges and sound walls on the San Diego Fwy. (I-405); while widening lanes from the Santa Monica Fwy. (I-10) to the Ventura Fwy. (US-101).
This project will reduce existing and forecasted traffic congestion on the I-405 and enhance traffic operations by adding freeway capacity in an area that experiences heavy congestion. In addition to these modifications, the project will improve both existing and future mobility and enhance safety throughout the corridor.
Project benefits include a decrease in commuter time, reduction in air pollution, and promotion of ridesharing.
The I-405 Sepulveda Pass Improvements Project will:
Get construction updates on Twitter
| Date | Notice Brief | Detail |
|---|---|---|
|
August 23 |
On Monday, August 23, 2010, the contractor is anticipated to begin constructing a temporary sidewalk along the south side of Skirball Bridge. This will maintain pedestrian access throughout the upcoming demolition and reconstruction of the of the bridge’s north side. The right hand lane in the eastbound direction along Skirball Bridge will be closed for approximately four weeks to conduct this work. K-rail (concrete barriers) will be placed along the bridge to separate traffic from the work zone. This temporary sidewalk construction is part of early preparation work activities to support the Skirball Bridge demolition and reconstruction activity. Click here for Freeway Closures |
HTML |
|
August 17 |
Exxon Mobil will begin the temporary relocation of the utility line on the Caltrans right of way. This activity requires the nightly closure of the Sunset Bl-NB 405 on ramp. Click here for Freeway Closures |
HTML |
|
August 10 |
As part of the I-405 Project, Southern California Gas company (SCG) will relocate a gas line to Thurston Circle. This work is necessary for the construction of a wall on the east side of Sepulveda Bl. Click here for Freeway Closures |
HTML |
|
July 26 |
The Contractor will begin setting K-rail, clearing trees and plants, widening the freeway and constructing a sound wall east of the I-405 Freeway, from Ohio Av to Wilshire Bl. Daytime and nighttime work is anticipated to begin Monday, July 26, 2010, for approximately seven months. This activity will take place from 9pm to 5am and 7am to 3:30pm. Click here for Freeway Closures |
HTML |
|
July 19 |
The Contractor will begin clearing trees and plants, excavating bridge footings and drilling pile, north and south of Santa Monica Bl, east and west of the I-405 freeway, starting July 19, 2010. Click here for Freeway Closures |
HTML |
|
July 15 |
The Contractor will begin clearing trees and grubbing plans, removing soil, and building a retaining wall west of the southbound I-405 freeway, north of Constitution Av. starting July 15, 2010. Click here for Freeway Closures |
HTML |
|
July 12 |
The Contractor will begin clearing trees and plants, excavating soil and erecting a retaining wall east of the northbound I-405 Freeway, from Wilshire Bl to Montana Av. Night time work is anticipated to begin Monday, July 12, 2010, for approximately five months. This activity will take place from 9pm to 6am. |
HTML |
View Construction Notice Archives
Get construction updates on Twitter
| Activity | Closure Type | Closure | Opening |
|---|---|---|---|
| Day work | Lane | 9 am | 3 pm |
| Night work | Lane | 9 pm | 6 am |
| Activity | Closure Type | Closure | Opening |
|---|---|---|---|
| Mainline | Complete | Midnight | 6 am |
| Mainline | Lane | 7 pm | 6 am |
| Mainline | On-ramps | 7 pm | 6 am |
| Mainline | Off-ramps | 7 pm | 6 am |
| Freeway connector | Southbound I-405 to US 10 | 9 pm | 6 am |
| Freeway connector | US 10 to southbound I-405 | 10 pm | 6 am |
| Freeway connector | Southbound I-405 to US 101 | 7 pm | 6 am |
| Freeway connector | US 101 to southbound I-405 | 10 pm | 6 am |
| Activity | Closure Type | Closure | Opening |
|---|---|---|---|
| Mainline | Complete | Midnight | 6 am |
| Mainline | Lane | 7 pm | 6 am |
| Mainline | On-ramps | 7 pm | 6 am |
| Mainline | Off-ramps | 7 pm | 6 am |
| Freeway connector | Northbound I-405 to US 10 | 10 pm | 6 am |
| Freeway connector | US 10 to northbound I-405 | 9 pm | 6 am |
| Freeway connector | Northbound I-405 to US 101 | 9 pm | 6 am |
| Freeway connector | US 101 to northbound I-405 | 10 pm | 6 am |
Although there may be some variance in these times, the majority of closures occur during these times. The contractor may close a freeway ramp during day hours, although this would be a rare occurrence.
In effect: Monday, May 10, 2010, until further notice (approximately one year)
Location: Church Ln at Sunset Bl and Keil Av Montana Av and Sepulveda Bl
Eastbound: Regular route to Sunset Bl and Barrington Av then continue via Sunset Bl to (L) Church Ln, (R) Sepulveda Bl, (L) Montana Av/Gayley Av and regular route
Westbound: Regular route to Le Conte Av and Gayley Av, then continue via Gayley Av to (R) Veteran Av, (L) Sunset Bl, (R) Sepulveda Way, (R) Sepulveda Bl, (L) Church Ln and regular route
In effect: Monday, May 10, 2010 until further notice (approximately one year)
Location: Between Sunset/Church Ln and Montana/Veteran
Eastbound: Regular route to Sunset Bl and Barrington Av then continue via Sunset Bl
Only: to (L) Church Ln, (R) Sepulveda Bl, (L) Montana Av/Gayley Av and regular route.
Westbound: Regular route to Montana Av and Veteran Ave then (R) Veteran Av, (L) Sunset to Sunset/Church and regular route.
Please be aware that patrons on Lines 2-302, 4, 20, 704, 720, 761 and 920 will experience service delays and minor reroutes in service effective mid-March and lasting approximately three years due to construction on the I-405 Sepulveda Pass Improvements Project. Construction will impact bus service travelling along the freeway and through the construction zones between National Boulevard and Ventura Boulevard. The project includes the following features:
Please visit, metro.net/around/service-advisories/ for Bus Operations Service Updates.
Please visit these websites for information on transportation services provided in the Sepulveda Pass by agencies other than Metro:
Patrons will be impacted by freeway ramp closures, reductions in lane widths, soundwall construction and full freeway closure. Patrons should adjust their trip times along impacted corridors accordingly. For detour information, please visit www.metro.net/405.
Please accept our apologies for any inconvenience that you may experience during construction.
Community Relations Team:
Kasey Shuda - Wilshire Segment (National Bl to Waterford St)
Olga N. Arroyo - Sunset Segment (Waterford St to Sepulveda Bl)
Ron Macias - Mulholland Segment (Sepulveda Bl to Ventura Bl)
Ned Racine - New Media
Devon Cichoski - Manager
Yvette ZR Rapose - Manager, Capital Projects
Contact Information:
Metro Community Relations
6060 Center Dr, 2nd Fl
Los Angeles, CA 90045-2952
Tel: 213.922.3665
I405@metro.net
Sign up for our email list
Copyright © 2010 Metro - Los Angeles County Metropolitan Transportation Authority





