| Date | Notice |
|
July 29, 2010
|
The Metro Orange Line Extension Project contractor will begin removing hazardous soil along Canoga Av between Vanowen and Lassen streets. This activity is scheduled to begin Thursday, July 29, 2010 for the duration of approximately two weeks.
|
|
July 28, 2010
|
Metro Orange Line Extension Project Contractor will construct the abutments to support the new Lassen St overcrossing. This activity requires the Contractor to excavate, drill a pile foundation and erect abutment walls. This activity is scheduled to begin Wednesday, July 28, 2010 and the duration is for approximately two and half months.
|
|
July 22, 2010
|
Beginning at 6am on Thursday, July 22, 2010 through the end of construction summer 2012, a portion of the south parking lot will be used as a staging area by the Metro Orange Line Extension Contractor.
|
|
July 20, 2010
|
Metro’s Contractor will install k-rail and excavate boring pits to facilitate the undergrounding of the utilities on Lassen St between Owensmouth Av and Canoga Av. This activity is scheduled to begin Tuesday, July 20, 2010 and will last for approximately two months. Please see the attached Construction Notice for further details.
|
|
July 8, 2010
|
As part of the pre-construction activities for the Metro Orange Line Extension Project, the Contractor will perform utility survey on streets running along the Canoga Av. This activity requires street lane closures to facilitate the safe use of potholing equipment.
|
|
June 28, 2010
|
In preparation for construction of the Metro Orange Line Extension, the Contractor will install a vault on Lassen St just west of Remmet Av. The activity is scheduled to begin Monday, June 28, 2010 for duration of two days.
|
|
June 28, 2010
|
The Construction Notice is regarding the beginning of vacant property demolition along the Metro Orange Line Extension Project right-of-way. The work will begin Monday, June 28, 2010 and expected to last for approximately one month.
|
|
May 12, 2010
|
Contractor for the Metro Orange Line Extension Project begins lead and asbestos abatement on vacant structures along the right-of-way, slightly east of Canoga Avenue where the Metro Orange Line Extension will extend four miles.
|
|
March 29, 2010
|
Beginning Monday, March 29, 2010 the Contractor will begin the first stage of utility work on Lassen between Owensmouth and Canoga. The utility work will include removing overhead utility lines and placing them underground. Activities to expect are survey layout, saw cutting, restriping, trenching, conduit, vault placement and repaving.
|
|
March 22, 2010
|
Beginning at 6am on Monday, March 22, 2010 through the end of construction in summer of 2012, a portion of the south parking lot will be used as a staging area by the Metro Orange Line Extension Contractor.
|
|
April 6, 2009
|
Beginning Monday, April 6, 2009, Qwest Communications will start work on their existing fiber optic facilities in the north parking lot of the Chatsworth Station. The work involves exposing the existing fiber optic and providing concrete encasement protection.
|