Construction Notices

Get construction updates on Twitter

Date Notice Brief Detail

September 22

Wilshire/La Cienega: 17 Full Weekend Closures

In the Wilshire/La Cienega area, decking will occur on Wilshire Bl between San Vicente Bl and mid-way into the Wilshire Bl/La Cienega Bl intersection.

More information about Wilshire/La Cienega: 17 Full Weekend Closures in HTML format

September 15

October Closures for Wilshire/Western Pile Installation

Starting in mid-October, pile installation will occur on Wilshire Blvd. between Western Ave. and Manhattan Pl. and within the staging yard located at Wilshire/Manhattan Pl. 

More information about October Closures for Wilshire/Western Pile Installation in HTML format

September 15

Construction Week Look Ahead (City of LA + City of Beverly Hills)

Beginning Monday, September 18th thru Friday, September 22nd the design-builder will be conducting:

More information about Construction Week Look Ahead (City of LA + City of Beverly Hills) in HTML format

September 15

Wilshire/La Cienega Phase 1: Wilshire Blvd. Full Closure

Beginning Friday, September 15 at 8pm through Monday, September 18, at 6am there will be a full closure of Wilshire Blvd. between La Cienega Blvd. and San Vicente Blvd. 

More information about Wilshire/La Cienega Phase 1: Wilshire Blvd. Full Closure in HTML format

September 14

하수도관 재배치 공사를 위한 Crenshaw 불러바드 동방향 Wilshire불러바드의 폐쇄

9월 16일 (토) 오전 2시부터 오후 11시까지, Wilshire Blvd.와 Western Ave. 교차로 서쪽에 있는 하수도 시스템을 재배치 하기 위해 동방향 Wilshire Blvd.를 폐쇄하게 됩니다. 이 작업으로 인한 교통 통제 구간은 다음과 같습니다.

More information about 하수도관 재배치 공사를 위한 Crenshaw 불러바드 동방향 Wilshire불러바드의 폐쇄 in HTML format

September 14

Eastbound Wilshire Closure at Crenshaw for Sewer Relocation

On Saturday, September 16, from 2am – 11pm, there will be a closure of eastbound Wilshire Blvd. to allow for the relocation of a sewer system west of the Wilshire Blvd./Western Ave. intersection.

More information about Eastbound Wilshire Closure at Crenshaw for Sewer Relocation in HTML format

September 05

City of Beverly Hills - Wilshire/La Cienega: September Look-Ahead

This monthly notification is an outline of construction activities for the month of September 2017, pending City of Beverly Hills approval. 

More information about City of Beverly Hills - Wilshire/La Cienega: September Look-Ahead in HTML format

September 01

Beverly Hills Update: PM Utility Relocation Work for Wilshire/La Cienega Station

On Tuesday, September 5th through Wednesday, September 6th (8pm–6:30am), work will continue to perform conduit placement at the intersection of Tower Dr. and Wilshire Blvd.

More information about Beverly Hills Update: PM Utility Relocation Work for Wilshire/La Cienega Station in HTML format

August 25

Beverly Hills Update: PM Utility Relocation Work at Wilshire/La Cienega

On Sunday, August 27th  through Friday, September 1st  (8pm – 6:30am), work will continue to perform conduit placement at the intersection of Tower Dr. and Wilshire Blvd.

More information about Beverly Hills Update: PM Utility Relocation Work at Wilshire/La Cienega in HTML format

August 24

Instrumentation Work at Wilshire/Manhattan

On Saturday, August 26 from 7am to 5pm, there will be pot holing and utility investigation on Wilshire Blvd. between Western Ave. and Manhattan Pl.

More information about Instrumentation Work at Wilshire/Manhattan in HTML format

August 24

Wilshire Blvd./Manhattan Pl.의 중앙분리대 제거 작업

8월 26일 토요일 오전 7시부터 오후 5시까지, Western Ave. 및 Manhattan Pl. 사이 구간의 Wilshire Blvd. 상에서 구덩이 파는 작업및 공공설비 조사가 진행됩니다.

More information about Wilshire Blvd./Manhattan Pl.의 중앙분리대 제거 작업 in HTML format

August 24

Construcción en Wilshire Blvd./Manhattan Pl.

El sábado 26 de agosto, de 7am a 5pm, habrá perforación exploratoria e investigación de servicios públicos en Wilshire Blvd., entre Western Ave. y Manhattan Pl.

More information about Construcción en Wilshire Blvd./Manhattan Pl. in HTML format

August 15

Southern California Gas Utility Relocation at Century City/Constellation Station

On Tuesday, August 15th - Fall 2017, Metro contractors will be relocating Southern California Gas (SCG) utilities, Mondays - Thursdays from 7pm to 6am on Constellation Blvd. between Solar Way and Century Park East and Avenue of the Stars. 

More information about Southern California Gas Utility Relocation at Century City/Constellation Station in HTML format

August 14

Westbound Wilshire Blvd. Closure at La Brea Ave.

From Friday, August 18 at 9pm, through Saturday, August 19 at midnight, westbound Wilshire Blvd. will be closed between La Brea Ave. and Cloverdale Ave. to support jet grouting activities at Wilshire Blvd./ Cloverdale Ave. 

More information about Westbound Wilshire Blvd. Closure at La Brea Ave. in HTML format

August 09

Abatement of Non-Recyclable Construction Material Work at 9430 Wilshire Blvd.

Beginning Thursday, August 10th, and continuing daily 8am to 6pm for four weeks (except weekends and holidays), Metro contractors will be performing abatement of non-recyclable construction material work at 9430 Wilshire Blvd.

More information about Abatement of Non-Recyclable Construction Material Work at 9430 Wilshire Blvd. in HTML format

August 09

Abatement of Non-Recyclable Construction Material Work at 9430 Wilshire Blvd

Beginning Thursday, August 10th, and continuing daily 8am to 6pm for 4 weeks (except weekends and holidays), Metro contractors will be performing abatement of non-recyclable construction material work at 9430 Wilshire Blvd.

More information about Abatement of Non-Recyclable Construction Material Work at 9430 Wilshire Blvd in HTML format

August 04

Instrumentation Work at Wilshire Blvd./Tremaine Ave. & Wilshire Blvd./Hudson Ave.

From Monday, August 7 to Friday, August 11, there will be instrumentation work at Wilshire Blvd./Tremaine Ave. and Wilshire Blvd./Hudson Ave.

More information about Instrumentation Work at Wilshire Blvd./Tremaine Ave. & Wilshire Blvd./Hudson Ave. in HTML format

August 02

Update: Southern California Edison (SCE) Utility Civil Work - Wilshire Bl/El Camino Dr and Crescent Dr

The Purple Line Extension Subway Project, Section 2 will begin pre-construction work activities in the City of Beverly Hills beginning September 5, 2017 for the future Wilshire/Rodeo station which will be located on the southwest corner of Wilshire Blvd. and Reeves Dr.

More information about Update: Southern California Edison (SCE) Utility Civil Work - Wilshire Bl/El Camino Dr and Crescent Dr in HTML format

July 31

Jet Grouting at Wilshire Blvd./Cloverdale Ave.

On Saturday, August 12, jet grouting activities will move to a new location on Wilshire Blvd. between Cochran Ave. and Detroit St.  

More information about Jet Grouting at Wilshire Blvd./Cloverdale Ave. in HTML format

July 27

Wilshire Blvd./Sycamore Ave. – Delivery and Excavation Support

On Saturday, July 29 from 7am–5pm, La Brea Station excavation and material deliveries will require the following traffic control measures: 

More information about Wilshire Blvd./Sycamore Ave. – Delivery and Excavation Support in HTML format

July 26

Advanced Utility Relocation for Century City/Constellation Station Look-Ahead

This is an overview of ongoing advanced utility relocation for the Century City/Constellation Station thru Fall 2017.  

More information about Advanced Utility Relocation for Century City/Constellation Station Look-Ahead in HTML format

July 26

Lane Reduction for La Cienega Yard Decking

From Monday, July 31 – Sunday, August 20, decking activities will occur in the Wilshire/La Cienega staging yard and on the east side sidewalk of La Cienega Blvd.

More information about Lane Reduction for La Cienega Yard Decking in HTML format

July 20

Work Zone Removal: Wilshire/Crenshaw

On Saturday, July 22 from 3am – 5pm, the work zone at Wilshire Blvd./Crenshaw Blvd. will be removed. Wilshire Blvd. will be returned to three lanes in each direction and turn restrictions will be lifted in the area. 

More information about Work Zone Removal: Wilshire/Crenshaw in HTML format

July 19

Wilshire/La Cienega Piling

On Friday, July 21 at 9pm – Monday, July 24 at 6am, pile installation will occur in the Wilshire/La Cienega intersection. This work will involve the drilling and setting of piles, concrete work, and street restoration. 

More information about Wilshire/La Cienega Piling in HTML format

July 18

Wilshire/La Cienega Signal Work

Starting Thursday, July 20th thru Monday, July 24th electrical work will be performed on the Wilshire/La Cienega traffic signal. 

More information about Wilshire/La Cienega Signal Work in HTML format

July 18

Extended Closure of N. Hamilton Dr.

Starting Monday, July 24 – Sunday, August 13, N. Hamilton Dr. will be closed at Wilshire Blvd. to support pot holing and pile installation. Local access to N. Hamilton Dr. will be maintained from San Vicente Blvd. 

More information about Extended Closure of N. Hamilton Dr. in HTML format

July 12

Weekday Utility Relocation on Santa Fe Ave. between Willow St. and Palmetto St.

From Thursday, July 13 through Saturday, August 19, from 7am to 3:30pm, Metro contractors will be relocating utilities on the east side of South Santa Fe Ave. between Willow St. and Palmetto St. (Monday—Friday only.) 

More information about Weekday Utility Relocation on Santa Fe Ave. between Willow St. and Palmetto St. in HTML format

July 11

Fairfax Decking Maintenance & Street Restoration

Beginning Friday, July 14 at 9am – Sunday, July 16 at 6am, decking maintenance work will occur on Wilshire Blvd. and the work zone on the south side of Wilshire Blvd. will be removed. 

More information about Fairfax Decking Maintenance & Street Restoration in HTML format

June 29

Westbound Wilshire Blvd. Closure for Jet Grouting Activities

Starting Friday, July 7 at 9pm, through Sunday, July 9 at 7am, westbound Wilshire Blvd. will be closed between Crenshaw Blvd. and Mansfield Ave.

More information about Westbound Wilshire Blvd. Closure for Jet Grouting Activities in HTML format

June 14

La Cienega Paving

Starting Saturday, June 17 – Sunday, June 18, paving will occur in the Wilshire/La Cienega intersection. Work hours are 7am-10pm. 

More information about La Cienega Paving in HTML format

June 14

Fase 3: en Wilshire Bl, desde Fairfax Av hasta Crescent Heights Bl

A partir del  viernes, 16 de junio a las 8pm.  al  lunes 19 de junio, a las 6am  habrá un cierre completo de Wilshire Blvd. entre Fairfax Ave. y Crescent Heights Blvd. 

More information about Fase 3: en Wilshire Bl, desde Fairfax Av hasta Crescent Heights Bl in HTML format

June 14

3단계: Wilshire Bl, Fairfax Av부터 Crescent Heights Bl까지

6월 16일 금요일 오후 8시부터  6월 19일 월요일  오전 6시까지 Wilshire Blvd.가 Fairfax Ave.와 Crescent Heights Blvd. 사이 구간이 전면 폐쇄됩니다.

More information about 3단계: Wilshire Bl, Fairfax Av부터 Crescent Heights Bl까지 in HTML format

June 14

Phase 3: Wilshire Bl, Fairfax Av to Crescent Heights Bl

Beginning Friday, June 16 at 8pm through Monday, June 19, at 6am there will be a full closure of the Wilshire Blvd. between Fairfax Ave. and Crescent Heights Blvd. 

More information about Phase 3: Wilshire Bl, Fairfax Av to Crescent Heights Bl in HTML format

June 13

Sidewalk Closure: Wilshire Blvd./Manhattan Pl.

From 7am to 4pm on Thursday, June 15, Friday, June 16, and Monday, June 19, there will be utility investigation on the sidewalk along the north side of Wilshire Blvd. between Manhattan Pl. and Western Ave.

More information about Sidewalk Closure: Wilshire Blvd./Manhattan Pl. in HTML format

June 09

Restoration Work - Sidewalk Closure, Wilshire/Gale Dr.

In preparation for the upcoming work zone switch to the north side of Wilshire Blvd., the sidewalk on the south side of Wilshire Blvd. between Gale Dr. and the US Renal Center will be closed through Friday, June 16th.  

More information about Restoration Work - Sidewalk Closure, Wilshire/Gale Dr. in HTML format

June 06

Advanced Utility Relocation: DWP (Power) On Constellation Blvd. between Avenue of the Stars and Century Park East

Beginning Wednesday, June 7th, Metro contractors will continue relocating DWP (Power) utilities for Section 2 of the Purple Line Extension on Constellation Blvd. between Avenue of the Stars and Century Park East.

More information about Advanced Utility Relocation: DWP (Power) On Constellation Blvd. between Avenue of the Stars and Century Park East in HTML format

May 31

Update: La Cienega Pile Installation

On Saturday, June 3 – Sunday, June 4, pile installation will continue in the Wilshire/La Cienega intersection. Work hours are 7am-8pm for the drilling and setting of piles, and 8pm-10pm for concrete and support activities.

More information about Update: La Cienega Pile Installation in HTML format

May 31

Westbound Wilshire Blvd. Closure for Jet Grouting Activities

Starting Friday, June 2 at 9pm, through Sunday, June 4 at 7am, westbound Wilshire Blvd. will be closed between Crenshaw Blvd. and Windsor Ave. to support jet grouting activities at Wilshire Bl./Crenshaw Blvd. Lane reductions will start on westbound Wilshire Blvd. at Norton Ave. leading to the closure at Crenshaw Blvd.

More information about Westbound Wilshire Blvd. Closure for Jet Grouting Activities in HTML format

May 30

Inyección de concreto: Wilshire Blvd./Highland Ave.

A partir del viernes 9 de junio, las actividades de inyección de concreto continuarán en Wilshire Blvd. en nuevas ubicaciones cerca de la intersección de Wilshire Blvd. y Highland Ave.

More information about Inyección de concreto: Wilshire Blvd./Highland Ave. in HTML format

May 25

Advanced Utility Relocation Work

Beginning Tuesday, May 30th, Metro contractors will continue relocating DWP (water) utilities for Section 2 of the Purple Line Extension under extended work hours from 7am to 8pm on weekdays. The work will include excavation and trenching for the installation of a water main and fire hydrant, installation of traffic control devices, and trench plates on Constellation Boulevard from Avenue of the Stars to Century Park East

More information about Advanced Utility Relocation Work in HTML format

May 24

Jet Grouting - Wilshire Blvd./Highland Ave.

The design-builder anticipates Friday, June 9, as the date when jet grouting activities will continue on Wilshire Blvd. in new locations near the Wilshire Blvd./Highland Ave. intersection.

More information about Jet Grouting - Wilshire Blvd./Highland Ave. in HTML format

May 19

Century City to Westwood

Metro contractors are performing field work as part of the planning for Section 3 of the Purple Line Extension. The current work will include groundwater pump testing including a step drawdown for a period of about 6 to 8 hours and a continuous 24 to 48 hours (overnight) constant rate pump test.

More information about Century City to Westwood in HTML format

May 18

Jet Grouting Traffic Control Installation at Wilshire/Crenshaw

On Friday, May 19 from 8pm thru Saturday, May 20 at 11pm, there will be intermittent lane reductions to support street restriping and K-rail installation on Wilshire Blvd. between Wilshire Blvd./Crenshaw Blvd. and Wilshire Blvd./Western Ave. 

More information about Jet Grouting Traffic Control Installation at Wilshire/Crenshaw in HTML format

May 05

Jet Grouting – Wilshire Blvd. (Windsor Blvd. to Bronson Ave.)

Beginning Friday, May 19, jet grouting activities will continue on Wilshire Blvd. in a new location at Wilshire Blvd./Crenshaw Blvd. 

More information about Jet Grouting – Wilshire Blvd. (Windsor Blvd. to Bronson Ave.) in HTML format

May 05

Extended Closure of North Gale Drive

Starting Saturday, May 20 thru mid-2018*, Gale Dr. will be closed just north of Wilshire Blvd. to safely support pile installation, street decking, excavation, and associated construction activities.

More information about Extended Closure of North Gale Drive in HTML format

April 25

City of Beverly Hills - Wilshire/La Cienega: May Look Ahead

This monthly notification is an outline of construction activities for the month of May 2017.

More information about City of Beverly Hills - Wilshire/La Cienega: May Look Ahead in HTML format

April 23

Field Work – Century City to Westwood

Metro contractors are performing field work as part of the planning for Section 3 of the Purple Line Extension. The current work will include geophysical testing to gather further information about the geological conditions. 

More information about Field Work – Century City to Westwood in HTML format

April 12

Pot Holing & Jet Grouting - Wilshire/Tower Dr.

Starting, Thursday, April 19 – Saturday, June 10, (anticipated end date) Tower Dr. will be closed at Wilshire Blvd. to support jet grouting construction at the intersection of Wilshire Blvd. and Tower Dr. 

More information about Pot Holing & Jet Grouting - Wilshire/Tower Dr. in HTML format

April 05

Fairfax Decking, Phase 1: Wilshire Blvd. from Fairfax Ave. - Spaulding Ave.

Beginning Friday, April 7 at 8pm thru Monday, April 10 at 6am, there will be a full closure of Wilshire Blvd. from Fairfax Ave. to Spaulding Ave. to support the start of the Fairfax decking operation.

More information about Fairfax Decking, Phase 1: Wilshire Blvd. from Fairfax Ave. - Spaulding Ave. in HTML format

April 03

Wilshire Blvd./Detroit St. Paving

From Thursday, April 6 to Friday, April 7, there will be paving and street restoration at Wilshire/Detroit that will require a full closure on the north side of Detroit St. at Wilshire Blvd. 

More information about Wilshire Blvd./Detroit St. Paving in HTML format

March 29

Fairfax 데킹, 1 단계: Fairfax Ave.부터 Spaulding Ave.까지의 Wilshire Blvd.

4월 7일 금요일 오후 8시부터 시작하여 4월 10일 월요일 오전 6시까지, Fairfax 데킹 작업 시작을 지원하기 위해 Wilshire Blvd.가 Fairfax Ave.부터 Spaulding Ave.까지 전면 폐쇄됩니다.

More information about Fairfax 데킹, 1 단계: Fairfax Ave.부터 Spaulding Ave.까지의 Wilshire Blvd. in HTML format

March 29

Entablado de Fairfax, fase 1: Wilshire Blvd. desde Fairfax Ave. hasta Spaulding Ave.

A partir del viernes 7 de abril a las 8pm y hasta el lunes 10 de abril a las 6am, Wilshire Blvd. estará cerrado desde Fairfax Ave. hasta Spaulding Ave. para dar inicio al trabajo de entablado de Fairfax.

More information about Entablado de Fairfax, fase 1: Wilshire Blvd. desde Fairfax Ave. hasta Spaulding Ave. in HTML format

March 27

Beverly Hills: 1-Hour Parking Validation Program

Due to construction activities at Wilshire Blvd./La Cienega Blvd., Metro has launched a 1-hour parking validation program to provide replacement parking for metered spots on Wilshire Blvd between San Vicente and La Cienega.     

More information about Beverly Hills: 1-Hour Parking Validation Program in HTML format

March 23

Traffic Switch at Wilshire/La Brea for Center Opening

On Friday, March 24 at 9pm through Sunday, March 26 at midnight, the current work zone on the south side of Wilshire Blvd. at La Brea Ave. will be removed and partially replaced with a work zone in the center lanes of Wilshire Blvd. at Wilshire Blvd./Sycamore Ave.

More information about Traffic Switch at Wilshire/La Brea for Center Opening in HTML format

March 21

Uber/Lyft: 10-minute Customer Loading Zone for 8383 Wilshire

To promote public safety, a new 10-minute customer loading zone has been in installed in the City of Beverly Hills on San Vicente Bl. for access to the 8383 Wilshire building.

More information about Uber/Lyft: 10-minute Customer Loading Zone for 8383 Wilshire in HTML format

March 21

Uber/Lyft: Prohibido el ascenso y descenso en Gale Dr

Para promover la seguridad pública, se instaló una zona de ascenso de 10 minutos para clientes en la ciudad de Beverly Hills en San Vicente Bl. para el acceso al edificio 8383 Wilshire.

More information about Uber/Lyft: Prohibido el ascenso y descenso en Gale Dr in HTML format

March 21

Uber/Lyft: Gale Dr 상 승차/하차 금지

공공 안전 진흥을 위해, 비벌리힐스 시의 San Vicente Bl. 상에 8383 Wilshire 빌딩에 접근하기 위한 10분 승객 탑승구역이 신설되었습니다. Uber 및 Lyft 기사는 8383 Wilshire 빌딩의 승객들을 정해진 장소에서 승차 및 하차해 주실 것을 권합니다.

More information about Uber/Lyft: Gale Dr 상 승차/하차 금지 in HTML format

February 24

Beverly Hills Update: Intermittent Street Closures for Pre-Piling Activities at Wilshire/La Cienega

Starting Wednesday, March 1 to Friday, March 31, pre-piling work will occur on S. Gale Dr. and S. Hamilton Dr. and will require intermittent closures of these streets at Wilshire Blvd. 

More information about Beverly Hills Update: Intermittent Street Closures for Pre-Piling Activities at Wilshire/La Cienega in HTML format

February 02

La Cienega Pre-Piling and Pot Holing

Starting Monday, February 6th thru March 2017, pre-piling and pot holing activities will occur in the Wilshire Blvd./La Cienega Blvd. area.

More information about La Cienega Pre-Piling and Pot Holing in HTML format

January 25

Las actividades de jet grouting se desplazan al este en Wilshire Blvd.

A partir del viernes 17 de febrero, las actividades de jet grouting seguirán en Wilshire Blvd., en las nuevas ubicaciones, de Wilshire Blvd. a Wilton Pl. y de Wilshire Blvd. a St. Andrews Pl. 

More information about Las actividades de jet grouting se desplazan al este en Wilshire Blvd. in HTML format

January 25

그라우트 분사 작업이 Wilshire Blvd. 동쪽으로 이동합니다.

2월 17일 금요일부터 그라우트 분사 공사가 Wilshire Blvd.의 또 다른 구역인 Wilshire Blvd./Wilton Pl. 및 Wilshire Blvd./St. Andrews Pl.

More information about 그라우트 분사 작업이 Wilshire Blvd. 동쪽으로 이동합니다. in HTML format

January 25

Jet Grouting Moves East on Wilshire Blvd. (Extended Notice: 8 - 12 weeks)

Beginning Friday, February 17, jet grouting activities will continue on Wilshire Blvd. in new locations at Wilshire Blvd./Wilton Pl. and Wilshire Blvd./St. Andrews Pl.

More information about Jet Grouting Moves East on Wilshire Blvd. (Extended Notice: 8 - 12 weeks) in HTML format

January 13

K−Rail and Traffic Control Installation at Wilshire/La Cienega

In preparation for future pile installation of the La Cienega Station, the contractor will be installing k−rail (concrete barriers) and fencing on the south side of Wilshire Blvd between La Cienega Blvd. and San Vicente Blvd. This installation is anticipated to take place over the weekend of February 4th 2017.

More information about K−Rail and Traffic Control Installation at Wilshire/La Cienega in HTML format

December 07

Fairfax Station Piling Work

Pile work on the south side of Wilshire Blvd. from just west of Fairfax Ave. to Ogden Dr. will continue through April of 2017. Long-term temporary work zones will be in place for an anticipated 3 to 4 months, sidewalks will be closed to support piling and decking.   

More information about Fairfax Station Piling Work in HTML format

November 02

Section 2 Field Work

Metro contractors continue to perform utility relocation work for Section 2 of the Purple Line Extension.

More information about Section 2 Field Work in HTML format

September 05

Section 2: Field Work

Metro contractors will be performing construction activities to relocate telecommunication lines for Section 2 of the Purple Line Extension. Work includes excavation and trenching and installation of traffic control devices and trench plates.  Work will take place west of Avenue of the Stars on Constellation Blvd.

More information about Section 2: Field Work in HTML format

August 15

Section 2: Field Work

Metro contractors will be performing construction activities to relocate utility lines for Section 2 of the Purple Line Extension. Work will take place on Constellation Blvd., west of Avenue of the Stars, for the next few months.

More information about Section 2: Field Work in HTML format