Construction Notices

Construction Notices

Get construction updates on Twitter

Start Date Notice Brief More Info

07/19/2019

Weekly Construction Look-Ahead (City of LA + City of Beverly Hills)
Segment: Wilshire
Area: Purple Line Section 1

This is the look-ahead for construction activities beginning Monday, July 22 through Friday, July 26 for Purple Line Extension Section 1.

More information about Weekly Construction Look-Ahead (City of LA + City of Beverly Hills) in HTML format

07/18/2019

Sanitary Sewer Inspection on Ohio Ave. between Federal Ave. & Colby Ave.
Area: Ohio/Federal, Ohio/Colby

On Thursday, July 25, investigation work will begin on Ohio Ave. between Federal Ave. and Colby Ave. from 9am to 3:30pm.

More information about Sanitary Sewer Inspection on Ohio Ave. between Federal Ave. & Colby Ave. in HTML format

07/18/2019

Utility Potholing Work on Avenue of the Stars at Constellation Blvd.
Area: Constellation/Avenue of the Stars

Preparation activities include potholing at the intersection of Avenue of the Stars/Constellation Blvd. to locate and identify underground utilities near the west side of the station box. 

More information about Utility Potholing Work on Avenue of the Stars at Constellation Blvd. in HTML format

07/17/2019

Piling Installation for Wilshire/Rodeo to Begin September 2019 through May 2020
Area: Wilshire/Beverly, Wilshire/Canon

Piling operations are anticipated to begin as early as September 23, 2019, and continue through May 2020*. 

More information about Piling Installation for Wilshire/Rodeo to Begin September 2019 through May 2020 in HTML format

07/17/2019

Purple Line Extension Community Meetings & Events
Area: Purple Line Extension

Purple Line Extension Transit Projects community meetings and events. 

More information about Purple Line Extension Community Meetings & Events in HTML format

07/16/2019

Ogden Dr. Closure
Area: Wilshire/Ogden

Concrete deliveries from the Ogden Staging Yard to the Fairfax Station are anticipated to continue through August 2019. 

More information about Ogden Dr. Closure in HTML format

07/15/2019

Weekend Utility Work on Wilshire Blvd. between El Camino Dr. and Crescent Dr.
Area: Wilshire/El Camino, Wilshire/Crescent

The design-build contractor for the Purple Line Extension Project Section 2 continues utility work on Wilshire Blvd. between El Camino Dr. and Crescent Dr. 

More information about Weekend Utility Work on Wilshire Blvd. between El Camino Dr. and Crescent Dr. in HTML format

07/15/2019

Lane Reduction on Wilshire Blvd. between Gale Dr. and San Vicente Blvd.
Area: Wilshire/Gale, Wilshire/San Vicente

From Tuesday, July 23 through Thursday, July 25, eastbound Wilshire Blvd. between Gale Dr. and San Vicente Blvd. will be reduced to two lanes from 9am to 3:30pm. 

More information about Lane Reduction on Wilshire Blvd. between Gale Dr. and San Vicente Blvd. in HTML format

07/12/2019

Updated: Sewer Work at Wilshire Blvd. Alley between N. Cañon Dr. and N. Crescent Dr.
Area: Wilshire/Beverly

The design-build contractor for the Purple Line Extension Project Section 2 continues sewer line replacement and relocation on Wilshire Blvd. between Beverly Dr. and Crescent Dr. Closure of the alley on the north side of Wilshire Blvd. between N. Cañon Dr. and N. Crescent Dr. and closure of the westbound curb lane on Wilshire Blvd. beginning July 18, 2019 for an estimated two weeks.* A flagger will be available at the alley to control traffic. 

More information about Updated: Sewer Work at Wilshire Blvd. Alley between N. Cañon Dr. and N. Crescent Dr. in HTML format

07/11/2019

Sewer Work at Wilshire Blvd. Alley between Beverly Dr. and N. Cañon Dr.
Area: Wilshire/Beverly

The design-build contractor for the Purple Line Extension Project Section 2 continues sewer line replacement and relocation on Wilshire Blvd. between Beverly Dr. and N. Cañon Dr. Intermittent closure of the alley on the north side of Wilshire Blvd. between Beverly Dr. and N. Cañon Dr. and the westbound curb lane on Wilshire Blvd. is required beginning July 18, 2019 for an estimated two weeks.*

More information about Sewer Work at Wilshire Blvd. Alley between Beverly Dr. and N. Cañon Dr. in HTML format

07/11/2019

Updated: Lane Closures for Installation of Geotechnical Instrumentation
Area: Wilshire/Reeves

Beginning June 24, 2019, the design-build contractor will begin the installation of instruments within the station box area to monitor ground movement, settlement and other geological conditions during construction. 

More information about Updated: Lane Closures for Installation of Geotechnical Instrumentation in HTML format

07/11/2019

Bus Pad Restoration at Wilshire Blvd./McCadden Pl.
Area: Wilshire Blvd./McCadden Pl.

Beginning Friday, July 19 at 7am, and continuing through Monday, July 22 at 6am, westbound Wilshire Blvd. will be reduced to one lane between June St. and Highland Ave. to restore a Wilshire Blvd. bus pad.

More information about Bus Pad Restoration at Wilshire Blvd./McCadden Pl. in HTML format

07/10/2019

Subsurface Investigation Work on Missouri Ave. west of Fox Hills Dr.
Area: Missouri/Fox Hills

From Friday, July 12 to Wednesday, July 17 work will occur on Missouri Ave., west of Fox Hills Dr. from 8am to 6pm, weekdays only. 

More information about Subsurface Investigation Work on Missouri Ave. west of Fox Hills Dr. in HTML format

07/10/2019

Subsurface Investigation Work on Eastborne Ave., west of Comstock Ave.
Area: Eastborne/Comstock

From Tuesday, July 16 to Friday, July 19 work will occur on Eastborne Ave., west of Comstock Ave. from 8am to 6pm.

More information about Subsurface Investigation Work on Eastborne Ave., west of Comstock Ave. in HTML format

07/03/2019

Century City/Constellation Station Monthly Look-Ahead for July
Area: Century City

This monthly notification is an outline of construction activities for the month of July 2019. Additional notices detailing these activities will be sent by email through the Purple Line Extension, Section 2 database.

More information about Century City/Constellation Station Monthly Look-Ahead for July in HTML format

07/02/2019

Subsurface Investigation Work on Santa Monica Blvd. (Frontage Rd.)
Area: Santa Monica/Frontage

From Wednesday, July 10 to Friday, July 12 work will occur on Santa Monica Blvd. (Frontage Rd.), south of Fox Hills Dr. from 9am to 3:30pm.

More information about Subsurface Investigation Work on Santa Monica Blvd. (Frontage Rd.) in HTML format

07/02/2019

Parking Restrictions on Wilshire Blvd. and Manhattan Pl.
Area: Wilshire/Manhattan

Beginning Monday, July 8, and continuing through Friday, July 12, parking restrictions will be posted from 6pm to 6am along sections of Wilshire Blvd. and Manhattan Pl. to allow components of the tunnel boring machines (TBMs) to be relocated from the Western staging yard to the Wilshire/La Brea Station.

More information about Parking Restrictions on Wilshire Blvd. and Manhattan Pl. in HTML format

07/02/2019

Subsurface Investigation Work on Rochester Ave.
Area: Rochester/Thayer, Rochester/Fairfburn

From Monday, July 8 to Thursday, July 11 work will occur on Rochester Ave., south of Thayer Blvd. north of Fairburn Ave. from 8am to 6pm.

More information about Subsurface Investigation Work on Rochester Ave. in HTML format

06/28/2019

Westwood/UCLA and Westwood/Va Hospital Look-Ahead for July
Area: Westwood

Metro contractors are continuing excavation work to relocate underground water, power and telecommunications equipment in Westwood. Advanced utility relocation (AUR) is expected to be completed in 2020. 

More information about Westwood/UCLA and Westwood/Va Hospital Look-Ahead for July in HTML format

06/28/2019

Sanitary Sewer Inspection on Ohio Ave. between Colby Ave. & Purdue Ave.
Area: Ohio/Colby, Ohio/Purdue

On Tuesday, July 2, investigation work will begin on Ohio Ave. between Colby Ave. and Purdue Ave. from 9am to 3:30pm.

More information about Sanitary Sewer Inspection on Ohio Ave. between Colby Ave. & Purdue Ave. in HTML format

06/27/2019

Westbound Wilshire Blvd. Closure at Western Ave.
Area: Wilshire/Western

Beginning Monday, July 8, and continuing through Monday, July 15, westbound Wilshire Blvd. will close to all traffic at Western Ave. from midnight to 6am. 

More information about Westbound Wilshire Blvd. Closure at Western Ave. in HTML format

06/27/2019

Wilshire/La Cienega Station Monthly Look-Ahead for July
Segment: Wilshire
Area: Wilshire/La Cienega

This monthly notification is an outline of construction activities for the month of July 2019, pending City of Beverly Hills approval.

More information about Wilshire/La Cienega Station Monthly Look-Ahead for July in HTML format

06/27/2019

Wilshire/Rodeo Station Monthly Look-Ahead for July
Area: Wilshire/Rodeo

This monthly notification is an outline of construction activities related to the Wilshire/Rodeo Station for the month of July 2019. 

More information about Wilshire/Rodeo Station Monthly Look-Ahead for July in HTML format

06/26/2019

Traffic Signal Installation on Santa Monica Blvd. at Century Park East for Bus Layover
Area: Santa Monica/Century Park East

This work will begin Thursday, June 27, 2019 beginning at 7pm and will continue through 6am on Friday, June 28, 2019. 

More information about Traffic Signal Installation on Santa Monica Blvd. at Century Park East for Bus Layover in HTML format

06/24/2019

Subsurface Investigation Work on Century Park West between Santa Monica Blvd. and Constellation Blvd.
Area: Santa Monica/Constellation

From Thursday, June 27 to Wednesday, July 3 work will occur on Century Park West between Santa Monica Blvd. and Constellation Blvd. from 9am to 3:30pm, weekdays only.

More information about Subsurface Investigation Work on Century Park West between Santa Monica Blvd. and Constellation Blvd. in HTML format

06/24/2019

Subsurface Investigation Work on Ashton Ave. between Westholme Ave. and Fairburn Ave.
Area: Ashton/Westholme, Ashton/Fairfburn

From Thursday, June 27 to Wednesday, July 3 work will occur on Ashton Ave., between Westholme Ave. and Fairburn Ave. from 8am to 6pm, weekdays only.

More information about Subsurface Investigation Work on Ashton Ave. between Westholme Ave. and Fairburn Ave. in HTML format

06/20/2019

Parking and Traffic Restrictions for Sanitary Sewer Inspection on Ohio Ave.
Area: Ohio/Purdue, Ohio/Butler

 On Tuesday, June 25, inspection work will begin on Ohio Ave. between Purdue Ave. and Butler Ave. from 9am to 3:30pm.

More information about Parking and Traffic Restrictions for Sanitary Sewer Inspection on Ohio Ave. in HTML format

06/18/2019

Subsurface Investigation Work on Pandora Ave.
Area: Pandora

On Friday, June 21 to Wednesday, June 26 work will occur on Pandora Ave., south of Kinnard Ave. north of Holman Ave.

More information about Subsurface Investigation Work on Pandora Ave. in HTML format

06/18/2019

Sidewalk Reduction Near N. Cañon Staging Yard and Sound Wall Installation
Area: Wilshire/Canon

Beginning June 24, 2019, the design-build contractor will begin sidewalk repairs adjacent to the N. Cañon staging yard and the installation of sound walls around the perimeter of the yard. 

More information about Sidewalk Reduction Near N. Cañon Staging Yard and Sound Wall Installation in HTML format

06/14/2019

Subsurface Investigation Work on Wellworth Ave. and Warner Ave.
Area: Wellworth/Fairfburn

Metro contractors will be investigating subsurface conditions also known as geotechnical investigation along the tunnel alignment of the Purple Line Extension Section 3 at various locations from June through August 2019.

More information about Subsurface Investigation Work on Wellworth Ave. and Warner Ave. in HTML format

06/13/2019

POSTPONED: Subsurface Investigation Work on Wilshire Blvd.
Area: Wilshire

Postponed until further notice. Work will occur on westbound Wilshire Blvd, east of Glendon Ave., in the center lanes.

More information about POSTPONED: Subsurface Investigation Work on Wilshire Blvd. in HTML format

05/21/2019

Update: Lane Reductions on Santa Monica Blvd. for Construction of Bus Layover
Area: Santa Monica/Avenue of the Stars, Santa Monica/Century Park East

From Tuesday, May 21 through Friday, July 19, the Purple Line Extension will continue bus layover work in Century City. 

More information about Update: Lane Reductions on Santa Monica Blvd. for Construction of Bus Layover in HTML format

05/15/2019

Update: Advance Utility Work on Constellation Blvd., west of Century Park East
Area: Constellation/Avenue of the Stars

Advanced utility relocation (AUR) will continue on the north side of Constellation Blvd., west of Century Park East. Work will also be done in the alley on the north side of Constellation Blvd.

More information about Update: Advance Utility Work on Constellation Blvd., west of Century Park East in HTML format

05/08/2019

Extended Work Hours at Wilshire/Western Yard: Summer 2019
Area: Wilshire/Western

Beginning mid-June 2019, work hours at the Wilshire/Western Staging Yard are expected to increase as tunneling operations turn west towards Wilshire/La Cienega Station.

More information about Extended Work Hours at Wilshire/Western Yard: Summer 2019 in HTML format

05/07/2019

Update: Sewer and Water Line Replacement and Relocation on Wilshire Blvd.
Area: Wilshire/Beverly, Wilshire/Crescent

The design-build contractor for the Purple Line Extension Project Section 2 will begin sewer and water line replacement and relocation on May 13, 2019 on Wilshire Blvd. between Beverly Dr. and Crescent Dr. 

More information about Update: Sewer and Water Line Replacement and Relocation on Wilshire Blvd. in HTML format

04/02/2019

Eastbound Wilshire Blvd. Directional Closure
Area: Wilshire/Fairfax, Wilshire/San Vicente

From Saturday, April 6 to Monday, April 8, eastbound Wilshire Blvd. between San Vicente Blvd. and Fairfax Ave. will be closed to through traffic. 

More information about Eastbound Wilshire Blvd. Directional Closure in HTML format

03/28/2019

Constellation Blvd. Closure at Century Park East, Beginning September 21
Area: Constellation/Century Park East

Constellation Blvd. at Century Park East will be closed to construct a launch box for the Purple Line Extension tunnel boring machines digging the twin tunnels for the underground subway through Century City.

More information about Constellation Blvd. Closure at Century Park East, Beginning September 21 in HTML format

03/27/2019

Westbound Wilshire Blvd. Directional Closure
Area: Wilshire/Fairfax, Wilshire/San Vicente

From Saturday, March 30 to Monday, April 1, westbound Wilshire Blvd. between Fairfax Ave. and San Vicente Blvd. will be closed to through traffic. 

More information about Westbound Wilshire Blvd. Directional Closure in HTML format

03/01/2019

Extended Hauling Hours at South La Brea Yard
Area: Wilshire/La Brea

Beginning the week of March 4, 2019, hours for hauling to and from the South La Brea staging yard will be extended. 

More information about Extended Hauling Hours at South La Brea Yard in HTML format

01/17/2019

Demolition of North Canon Properties and North Canon Dr. Closure
Area: Wilshire/Canon

Closure of N Canon Dr at Wilshire Bl starting April 2019 for approximately 24 months.

More information about Demolition of North Canon Properties and North Canon Dr. Closure in HTML format

03/21/2017

Uber/Lyft: 10-minute Customer Loading Zone for 8383 Wilshire
Area: Wilshire/San Vicente, Wilshire/Gale

To promote public safety, a new 10-minute customer loading zone has been in installed in the City of Beverly Hills on San Vicente Bl. for access to the 8383 Wilshire building.

More information about Uber/Lyft: 10-minute Customer Loading Zone for 8383 Wilshire in HTML format

03/21/2017

Uber/Lyft: Prohibido el ascenso y descenso en Gale Dr
Segment: Wilshire
Area: Wilshire/La Cienega, Wilshire/Gale

Para promover la seguridad pública, se instaló una zona de ascenso de 10 minutos para clientes en la ciudad de Beverly Hills en San Vicente Bl. para el acceso al edificio 8383 Wilshire.

More information about Uber/Lyft: Prohibido el ascenso y descenso en Gale Dr in HTML format

03/21/2017

Uber/Lyft: Gale Dr 상 승차/하차 금지
Area: Wilshire/La Cienega, Wilshire/Gale

공공 안전 진흥을 위해, 비벌리힐스 시의 San Vicente Bl. 상에 8383 Wilshire 빌딩에 접근하기 위한 10분 승객 탑승구역이 신설되었습니다. Uber 및 Lyft 기사는 8383 Wilshire 빌딩의 승객들을 정해진 장소에서 승차 및 하차해 주실 것을 권합니다.

More information about Uber/Lyft: Gale Dr 상 승차/하차 금지 in HTML format