07/31/2020

Weekly Construction Look-Ahead for Section 1 City of LA & City of Beverly Hills
Segment: Wilshire
Area: Purple Line Section 1

This is the look-ahead for construction activities beginning Monday, August 3 through Sunday, August 9 for Purple Line Extension Section 1.

More information about Weekly Construction Look-Ahead for Section 1 City of LA & City of Beverly Hills in HTML format

07/31/2020

Lane Reductions Between Stanley Dr. and San Vicente Blvd.
Area: Wilshire/Stanley, Wilshire/San Vicente

Beginning Monday, August 3 and continuing through Saturday, August 8, eastbound Wilshire Blvd. between Stanley Dr. and San Vicente Blvd. may be reduced to a single lane to support ongoing station construction activities occurring between La Cienega Blvd. and Gale Dr.

More information about Lane Reductions Between Stanley Dr. and San Vicente Blvd. in HTML format

07/30/2020

North Side Piling on Constellation Blvd. from Avenue of the Stars to Solar Way
Area: Constellation/Avenue of the Stars

Beginning August 4, piling will begin on the north side of Constellation Blvd. west of Avenue of the Stars to Solar Way. 

More information about North Side Piling on Constellation Blvd. from Avenue of the Stars to Solar Way in HTML format

07/29/2020

Purple Line Extension Community Meetings & Events
Area: Purple Line Extension

Purple Line Extension Transit Projects community meetings and events. 

More information about Purple Line Extension Community Meetings & Events in HTML format

07/29/2020

Westwood/VA Hospital Station Monthly Look-Ahead for August
Area: Westwood/VA Hospital

This monthly notification is an outline of construction activities for the Westwood/VA Hospital Station for the month of August 2020. 

More information about Westwood/VA Hospital Station Monthly Look-Ahead for August in HTML format

07/29/2020

Westwood/UCLA Station Monthly Look-Ahead for August
Area: Westwood/UCLA

This monthly notification is an outline of construction activities for the Westwood/UCLA Station during the month of August 2020. 

More information about Westwood/UCLA Station Monthly Look-Ahead for August in HTML format

07/28/2020

Wilshire/La Cienega Station Monthly Look-Ahead for August
Segment: Wilshire
Area: Wilshire/La Cienega

This monthly notification is an outline of construction activities for the month of August 2020. Pending City of Beverly Hills approval.*

More information about Wilshire/La Cienega Station Monthly Look-Ahead for August in HTML format

07/28/2020

Century City/Constellation Station Monthly Look-Ahead for August
Area: Century City

This monthly notification is an outline of construction activities for the month of August 2020. Additional notices detailing these activities will be sent by email through the Purple Line Extension, Section 2 database.

More information about Century City/Constellation Station Monthly Look-Ahead for August in HTML format

07/28/2020

Utility Surveys on Sepulveda Blvd. near Wilshire Blvd.
Area: Wilshire/Sepulveda

This pre-construction survey will be conducted from July 21 through August 7 from 9am to 3:30pm using a closed-circuit camera.

More information about Utility Surveys on Sepulveda Blvd. near Wilshire Blvd. in HTML format

07/24/2020

Appendage Work Zone Southwest Fairfax Ave. and Wilshire Blvd.
Area: Wilshire/Fairfax

Beginning Saturday, August 8 and continuing for one year, Wilshire Blvd. between San Diego Way and Spaulding Ave. will be reduced to two lanes in each direction

More information about Appendage Work Zone Southwest Fairfax Ave. and Wilshire Blvd. in HTML format

07/24/2020

Appendage Work Zone at Orange Dr. and Wilshire Blvd.
Area: Wilshire/Orange

Beginning Friday, August 28 and continuing through Saturday, February 27, 2021, Wilshire Blvd. between Detroit St. and June St. will be reduced to two lanes in each direction. Orange Dr. north of Wilshire Blvd. will be closed. 

More information about Appendage Work Zone at Orange Dr. and Wilshire Blvd. in HTML format

07/17/2020

Well-Monitoring in Century City
Area: Constellation/Century Park West

Metro contractors will continue conducting well-monitoring along the tunnel alignment of the Purple Line Extension Section 3 on Century Park West, from Saturday, July 25 through Sunday, July 26 from 8pm to 6am.

More information about Well-Monitoring in Century City in HTML format

07/17/2020

Lane Reductions Between La Cienega Blvd. and San Vicente Blvd.
Area: Wilshire/La Cienega

On Monday, July 13 and continuing through Saturday, July 18, and Monday, July 20 and continuing through Saturday, July 25, eastbound Wilshire Blvd. between La Cienega Blvd. and San Vicente Blvd. may be reduced to a single lane to support ongoing station construction activities.*

More information about Lane Reductions Between La Cienega Blvd. and San Vicente Blvd. in HTML format

07/17/2020

Geotechnical Instrumentation on Northbound I-405 Off-ramp
Area: I-405/Wilshire

Metro contractors will install geotechnical instrumentation monitors on the northbound I-405 off-ramp to westbound Wilshire Blvd. This work will be conducted from July 13 to 23, 9pm to 6am.

More information about Geotechnical Instrumentation on Northbound I-405 Off-ramp in HTML format

07/15/2020

Street Restoration on Wilshire Blvd.
Area: Wilshire/Gale, Wilshire/San Vicente

On Saturday, July 18, Wilshire Blvd. between Gale Dr. and San Vicente Blvd. will be intermittently restricted to one lane in each direction from 8am to 7pm. This traffic control will support ongoing street restoration efforts within the City of Beverly Hills.*

More information about Street Restoration on Wilshire Blvd. in HTML format

07/08/2020

Geotechnical Instrumentation on Southbound I-405 Off-ramp
Area: I-405/Wilshire

Metro contractors will install geotechnical instrumentation monitors on the southbound I-405 off-ramp to eastbound Wilshire Blvd. This work will be conducted from July 8 to 10, 10pm to 6am.

More information about Geotechnical Instrumentation on Southbound I-405 Off-ramp in HTML format

06/29/2020

Wilshire/Rodeo Station Monthly Look-Ahead for August
Area: Wilshire/Rodeo

This monthly notification is an outline of construction activities related to the Wilshire/Rodeo Station for the month of August 2020. 

More information about Wilshire/Rodeo Station Monthly Look-Ahead for August in HTML format

06/19/2020

Lane Reduction on Wilshire Blvd. between Stanley Dr. and Crescent Heights Blvd.
Area: Wilshire/Stanley, Wilshire/Crescent Heights

On Saturday, June 20, from 5am to 9pm, Wilshire Blvd. between Stanley Dr. and Crescent Heights Blvd. will be reduced to a single lane in each direction. 

More information about Lane Reduction on Wilshire Blvd. between Stanley Dr. and Crescent Heights Blvd. in HTML format

06/18/2020

Utility Surveys on Wilshire Blvd. and Federal Ave.
Area: Wilshire/Federal

This pre-construction survey activity will be done from Monday, June 22 to Friday, July 10, from 9pm to 6am. Utility services will be maintained.

More information about Utility Surveys on Wilshire Blvd. and Federal Ave. in HTML format

05/29/2020

Alley Closure between Johnnies and 99-Cents Only Store
Area: Wilshire/Fairfax

Anticipated to begin Monday, June 1, the alleyway between Johnnies and the 99-Cents Only Store will be intermittently closed for one year. 

More information about Alley Closure between Johnnies and 99-Cents Only Store in HTML format

05/27/2020

Work Zone Installation on Wilshire Blvd./Crescent Heights Blvd.
Area: Wilshire/Crescent Heights

Beginning Saturday, May 9, and continuing through Sunday, May 10, Wilshire Blvd. between La Jolla Ave. and Orange Grove Ave. will be reduced to a single lane in each direction. 

More information about Work Zone Installation on Wilshire Blvd./Crescent Heights Blvd. in HTML format

05/22/2020

Tunnel Investigation Work on Wilshire Blvd./San Vicente Blvd.
Area: Wilshire/San Vicente

Beginning Tuesday, May 26, and continuing through Friday, June 5, the intersection of Wilshire Blvd. and San Vicente Blvd. will experience multiple intermittent lane closures to support ongoing tunnel investigation work underneath Wilshire Blvd. 

More information about Tunnel Investigation Work on Wilshire Blvd./San Vicente Blvd. in HTML format

05/22/2020

Material Deliveries and Work Zone on Wilshire Blvd.
Area: Wilshire/Gale, Wilshire/Tower

Beginning the week of May 11, 2020, Wilshire Blvd. between San Vicente Blvd. and Hamilton Dr. will be reduced to two lanes in each direction. 

More information about Material Deliveries and Work Zone on Wilshire Blvd. in HTML format

05/18/2020

Utility Surveys on Sepulveda Blvd. near Wilshire Blvd.
Area: Sepulveda/Wilshire

This pre-construction survey is anticipated to take place between May 18 and May 22 from 9am to 3:30pm using a closed-circuit camera. The survey work will take one day to complete.

More information about Utility Surveys on Sepulveda Blvd. near Wilshire Blvd. in HTML format

05/14/2020

Geophysical Surveys in Century City
Area: Santa Monica/Beverly Glen

Metro contractors will conduct geophysical surveys along the tunnel alignment of the Purple Line Extension Section 3 on Santa Monica Blvd., from Monday, May 18 through Sunday, May 24 from 9pm to 6am.

More information about Geophysical Surveys in Century City in HTML format

05/12/2020

Well-Monitoring in Westwood
Area: Wilshire/Malcolm, Wilshire/Veteran

Metro contractors will continue conducting well-monitoring along the tunnel alignment of the Purple Line Extension Section 3 along Wilshire Blvd., between Malcolm Ave. and Veteran Ave., from Saturday, May 16 through Sunday, May 17 from 8pm to 6am.

More information about Well-Monitoring in Westwood in HTML format

05/12/2020

Well Maintenance at Wilshire Blvd./Detroit St.
Area: Wilshire/Detroit

On Wednesday, May 13 from 7am to 4pm, Detroit St. will be closed south of Wilshire Blvd. to support well maintenance work.

More information about Well Maintenance at Wilshire Blvd./Detroit St. in HTML format

05/11/2020

Well-Monitoring in Century City
Area: Constellation/Century Park West

Metro contractors will continue conducting well-monitoring along the tunnel alignment of the Purple Line Extension Section 3 at Constellation Blvd. and Century Park West, from Saturday, May 16 through Sunday, May 17 from 8pm to 6am.

More information about Well-Monitoring in Century City in HTML format

05/08/2020

Southern California Edison Cable Pulling on Wilshire Blvd. and Federal Ave.
Area: Wilshire/Federal

This upgrade will also provide power for the operations of the future Westwood/VA Hospital Station. From Monday, May 11 to Monday, May 18, Southern California Edison will pull electrical cable along Wilshire Blvd. and Federal Ave., from 10pm to 5am.

More information about Southern California Edison Cable Pulling on Wilshire Blvd. and Federal Ave. in HTML format

04/30/2020

Wilshire Blvd./Crescent Heights Blvd. K-Rail Work Zone Enclosures
Area: Wilshire/Crescent Heights

Two K-Rail work zones will be implemented to support ongoing mitigation efforts in the Wilshire Blvd./Crescent Heights Blvd. area starting Monday, May 11, 2020, through Friday, August 14, 2020. Street parking will be restricted.

More information about Wilshire Blvd./Crescent Heights Blvd. K-Rail Work Zone Enclosures in HTML format

04/28/2020

Extension of Orange Grove Ave. Closure at Wilshire Blvd.
Area: Wilshire/Orange Grove

The current anticipated date for Orange Grove Ave. restoration is January 2022. Access for residents will be maintained.

More information about Extension of Orange Grove Ave. Closure at Wilshire Blvd. in HTML format

04/24/2020

K-Rail Removal on Wilshire Blvd. at Sycamore Ave.
Area: Wilshire/Sycamore

On Sunday, April 26, the current K-Rail enclosure at Wilshire Blvd. at Sycamore Ave. will be removed. 

More information about K-Rail Removal on Wilshire Blvd. at Sycamore Ave. in HTML format

04/23/2020

K-Rail Enclosure on Wilshire Blvd. and Gale Dr.
Area: Wilshire/Gale

Beginning mid-May, a K-Rail enclosure will be in place on Wilshire Blvd. between Tower Dr. and Gale Dr. to create a work zone.

More information about K-Rail Enclosure on Wilshire Blvd. and Gale Dr. in HTML format

04/23/2020

Parking Restrictions on Wilshire Blvd., Ohio Ave. & Federal Ave.
Area: Wilshire/Ohio, Wilshire/Federal

Per the Los Angeles Department of Transportation (LADOT), there will be relaxed parking enforcement for street sweeping, however, parking restrictions in construction zones will still be enforced.

More information about Parking Restrictions on Wilshire Blvd., Ohio Ave. & Federal Ave. in HTML format

04/14/2020

Well-Monitoring in Westwood
Area: Wilshire

Metro contractors will begin conducting well-monitoring along the tunnel alignment of the Purple Line Extension Section 3 on Wilshire Blvd. from Saturday, April 18 through Sunday, Sunday 19 from 8pm to 6am.

More information about Well-Monitoring in Westwood in HTML format

04/13/2020

Utility Surveys on Bonsall Ave. Ramps at the West Los Angeles Veterans Affairs Medical Center Campus
Area: Wilshire/Bonsall

This pre-construction survey activity will be done on the Bonsall Ave. ramps from Monday, April 13 to Saturday, April 18, from 10pm to 5am.

More information about Utility Surveys on Bonsall Ave. Ramps at the West Los Angeles Veterans Affairs Medical Center Campus in HTML format

04/10/2020

Temporary Full Closure of Wilshire Blvd. from El Camino Dr. to Crescent Dr.
Area: Wilshire/El Camino, Wilshire/Crescent Dr

Beginning Monday, April 13, the contractor will extend the existing full closure west to El Camino Dr.

More information about Temporary Full Closure of Wilshire Blvd. from El Camino Dr. to Crescent Dr. in HTML format

04/02/2020

Lane Reductions, West Of Wilshire Blvd./La Cienega Blvd.
Area: Wilshire/La Cienega

Eastbound Wilshire Blvd. between Willaman Dr. and La Cienega Blvd. will be reduced to one lane on Saturday, April 4. 

More information about Lane Reductions, West Of Wilshire Blvd./La Cienega Blvd. in HTML format

04/02/2020

Eastbound Wilshire Blvd. Lane Reduction between Hamilton Dr. and San Vicente Blvd.
Area: Wilshire/Hamilton, Wilshire/San Vicente

Beginning Tuesday, March 10, and continuing through Saturday, April 4, Wilshire Blvd. will be intermittently reduced to one lane in each direction between Hamilton Dr. and San Vicente Blvd. Work hours are from 8pm to 7am. This traffic control will support ongoing subsurface investigation work underneath Wilshire Blvd.

More information about Eastbound Wilshire Blvd. Lane Reduction between Hamilton Dr. and San Vicente Blvd. in HTML format

03/27/2020

Request for Temporary Full Closure of Wilshire Blvd. During COVID-19 Restrictions
Area: Wilshire/Crescent, Wilshire/Beverly

Metro and the City of Beverly Hills have been exploring alternatives to help expedite the construction of the Wilshire/Rodeo Station. A full closure of Wilshire Blvd. between Crescent Dr. and Beverly Dr. was identified as a potential option to help work progress during the statewide pandemic health restrictions.

More information about Request for Temporary Full Closure of Wilshire Blvd. During COVID-19 Restrictions in HTML format

03/26/2020

Advanced Utility Relocation (AUR) on Midvale Ave.
Area: Midvale

Metro contractors are continuing excavation work to relocate underground water, power and telecommunications equipment in Westwood. Full street closure on Midvale Ave. from Monday, March 30 through Sunday, April 19.

More information about Advanced Utility Relocation (AUR) on Midvale Ave. in HTML format

03/17/2020

Lane Reductions on Wilshire Blvd., West of La Cienega Blvd.
Area: Wilshire/La Cienega

Westbound Wilshire Blvd. between Gale Dr. and Stanley Dr. will be reduced to one lane, and eastbound Wilshire Blvd. between Stanley Dr. and La Cienega Blvd. will be reduced to two lanes on Saturday, March 21. 

More information about Lane Reductions on Wilshire Blvd., West of La Cienega Blvd. in HTML format

03/12/2020

Subsurface Investigations on Constellation Blvd. near Solar Way
Area: Constellation/Solar

Investigations will be conducted on March 14 and 15 from 8pm to 6am. 

More information about Subsurface Investigations on Constellation Blvd. near Solar Way in HTML format

03/10/2020

Utility Relocation on Wilshire Blvd. near Federal Ave.
Area: Wilshire/Federal

Work will continue on Tuesday, March 10 and will be done in stages for the next several weeks, from 9pm to 6am.

More information about Utility Relocation on Wilshire Blvd. near Federal Ave. in HTML format

03/06/2020

Northbound Crescent Heights Blvd. Closure at Wilshire Blvd.
Area: Wilshire/Crescent Heights

Starting at 6am on Saturday, March 7 to 5am on Sunday, March 8 northbound McCarthy Vista/Crescent Heights Blvd. between San Vicente Blvd. and Orange St. may be closed to through traffic. 

More information about Northbound Crescent Heights Blvd. Closure at Wilshire Blvd. in HTML format

02/27/2020

Wilshire/Rodeo Geotechnical Instrumentation Installation
Area: Wilshire/Rodeo

Installations are expected to take place on Friday, February 25 through Tuesday, March 3 from 8am to 6pm. The work will occur along S. Linden Dr. between Wilshire Blvd. and Charleville Blvd. 

More information about Wilshire/Rodeo Geotechnical Instrumentation Installation in HTML format

02/26/2020

Utility Relocation on Wilshire Blvd. and Federal Ave.
Area: Wilshire/Federal

Work will continue on weekends starting Saturday, February 22 and will be done in stages for the next few weeks, 9pm to 6am on Wilshire Blvd. and 8am to 9am on Federal Ave.

More information about Utility Relocation on Wilshire Blvd. and Federal Ave. in HTML format

02/25/2020

Installation of Pedestrian Canopy on North Side Constellation Blvd.
Area: Constellation

Starting Tuesday, February 25 the construction contractor will be installing a pedestrian canopy over the north sidewalk on Constellation Blvd. adjacent to the full closure to provide protection during the tunnel boring operation. 

More information about Installation of Pedestrian Canopy on North Side Constellation Blvd. in HTML format

02/12/2020

Closures for Installation of Geotechnical Instrumentation in Beverly Hills
Area: Wilshire/Young/Lasky Dr/Moreno/Charleville/Spalding

The design-build contractor is continuing with installation of geotechnical instruments along the tunnel alignment and around the station box area in order to monitor ground movement, settlement, and other geological impacts from February 2020 through November 2020. 

More information about Closures for Installation of Geotechnical Instrumentation in Beverly Hills in HTML format

02/10/2020

Utility Relocation on Federal Ave., Ohio Ave., and Purdue Ave.
Area: Federal/Ohio/Purdue

Work will begin on Tuesday, February 11 and will be done in stages for the next several weeks, from 9am to 3:30pm.

More information about Utility Relocation on Federal Ave., Ohio Ave., and Purdue Ave. in HTML format

01/21/2020

Concrete Deliveries to the Wilshire/La Cienega Station
Area: Wilshire/La Cienega

Beginning Tuesday, January 28, the frequency of lane reductions are anticipated to increase to 2 to 3 times a week. 

More information about Concrete Deliveries to the Wilshire/La Cienega Station in HTML format

01/14/2020

Lane Closures for Wilshire Blvd./Beverly Dr. Intersection Piling
Area: Wilshire/Beverly

As part of the north side pile installation, the design-builder will install 27 piles across Beverly Dr. on the north side of Wilshire Blvd. beginning January 29 through April 2020. 

More information about Lane Closures for Wilshire Blvd./Beverly Dr. Intersection Piling in HTML format

01/02/2020

Constellation Blvd. Closure at Century Park East
Area: Constellation/Century Park East

Constellation Blvd. at Century Park East will be closed to construct a launch box for the Purple Line Extension tunnel boring machines digging the twin tunnels for the underground subway through Century City.

More information about Constellation Blvd. Closure at Century Park East in HTML format

10/07/2019

Update: Wilshire Blvd. Piling Activities to Begin October 9, 2019 through July 2020
Area: Wilshire/Beverly, Wilshire/Canon

Construction activities related to piling are anticipated to begin October 9, 2019 and continue through July 2020*. 

More information about Update: Wilshire Blvd. Piling Activities to Begin October 9, 2019 through July 2020 in HTML format

09/20/2019

Traffic Control to Support Concrete and Material Deliveries for Wilshire/La Cienega Station
Area: Wilshire/La Cienega

Concrete and material deliveries for the Wilshire/La Cienega Station are anticipated to begin in early October 2019. 

More information about Traffic Control to Support Concrete and Material Deliveries for Wilshire/La Cienega Station in HTML format

09/09/2019

Purple Line Extension Daily Traffic Update
Area: Purple Line Extension

Daily traffic impacts due to Purple Line Extension construction can be viewed on Waze and Google maps.

More information about Purple Line Extension Daily Traffic Update in HTML format

08/08/2019

Concrete and Rebar Deliveries at Wilshire/La Cienega
Area: Wilshire/La Cienega

Concrete and rebar deliveries to the Wilshire/La Cienega Station Box are anticipated to begin in September

More information about Concrete and Rebar Deliveries at Wilshire/La Cienega in HTML format

03/01/2019

Extended Hauling Hours at South La Brea Yard
Area: Wilshire/La Brea

Beginning the week of March 4, 2019, hours for hauling to and from the South La Brea staging yard will be extended. 

More information about Extended Hauling Hours at South La Brea Yard in HTML format

03/21/2017

Uber/Lyft: 10-minute Customer Loading Zone for 8383 Wilshire
Area: Wilshire/San Vicente, Wilshire/Gale

To promote public safety, a new 10-minute customer loading zone has been in installed in the City of Beverly Hills on San Vicente Bl. for access to the 8383 Wilshire building.

More information about Uber/Lyft: 10-minute Customer Loading Zone for 8383 Wilshire in HTML format

03/21/2017

Uber/Lyft: Prohibido el ascenso y descenso en Gale Dr
Segment: Wilshire
Area: Wilshire/La Cienega, Wilshire/Gale

Para promover la seguridad pública, se instaló una zona de ascenso de 10 minutos para clientes en la ciudad de Beverly Hills en San Vicente Bl. para el acceso al edificio 8383 Wilshire.

More information about Uber/Lyft: Prohibido el ascenso y descenso en Gale Dr in HTML format

03/21/2017

Uber/Lyft: Gale Dr 상 승차/하차 금지
Area: Wilshire/La Cienega, Wilshire/Gale

공공 안전 진흥을 위해, 비벌리힐스 시의 San Vicente Bl. 상에 8383 Wilshire 빌딩에 접근하기 위한 10분 승객 탑승구역이 신설되었습니다. Uber 및 Lyft 기사는 8383 Wilshire 빌딩의 승객들을 정해진 장소에서 승차 및 하차해 주실 것을 권합니다.

More information about Uber/Lyft: Gale Dr 상 승차/하차 금지 in HTML format