Project Schedule

Caltrans began the PS&E in February 2012.

Phase IA will deliver some safety related improvements earlier. Phase 1A construction was completed in November 2013.

Phase 1B is expected to be completed Winter 2015/2016 and construction is expected to begin in winter Winter 2014/2015.

Project Schedule *

PHASE COMPLETION
Complete Environmental Analysis Phase December 2010
Complete Final Engineering Phase 1A Fall 2012
Complete Final Engineering Phase 1B Fall 2013
Complete Construction Phase 1A Nov 2013
Start Construction Phase 1B Winter 2014/2015
Complete Construction Winter 2015/2016

* Preliminary Schedule, subject to change.