Construction Notices

Start Date Notice Brief More Info

02/14/2019

Utility Trench Work on Century Park East
Area: Constellation/Century Park East

Utility trench work will continue on Century Park East to install the underground utility infrastructure for the tunnel boring machines from the staging yard at 2040 Century Park East to the Launch Box on Constellation Blvd.  

More information about Utility Trench Work on Century Park East in HTML format

02/13/2019

Purple Line Extension Community Meetings & Events
Area: Purple Line Extension

Purple Line Extension Transit Projects community meetings and events. 

More information about Purple Line Extension Community Meetings & Events in HTML format

02/04/2019

Construction of Temporary Bus Layover on Santa Monica Blvd.
Area: Santa Monica/Avenue of the Stars, Santa Monica/Century Park East

The Purple Line Extension will continue bus layover work starting on February 25. Intermittent lane closures will be implemented throughout construction.

More information about Construction of Temporary Bus Layover on Santa Monica Blvd. in HTML format

01/31/2019

Nighttime Utility Work on Constellation Blvd.
Area: Constellation/Avenue of the Stars

Advanced Utility Relocation (AUR) for the LADWP and AT&T in Century City. 

More information about Nighttime Utility Work on Constellation Blvd. in HTML format

01/28/2019

Century City/Constellation Station Monthly Look-Ahead for February
Area: Century City

This monthly notification is an outline of construction activities for the month of February 2019. Additional notices detailing these activities will be sent by email through the Purple Line Extension, Section 2 database.

More information about Century City/Constellation Station Monthly Look-Ahead for February in HTML format

01/28/2019

Demolition of North Canon Properties (9383-9393 and 9395-9399 Wilshire Blvd.)
Area: Wilshire/Canon

The design-build contractor for Section 2 of the Purple Line Extension Project continues pre-construction work activities in Beverly Hills to prepare the North Canon Dr. construction staging yard located at 9383-9393 and 9395-9399 Wilshire Blvd.

More information about Demolition of North Canon Properties (9383-9393 and 9395-9399 Wilshire Blvd.) in HTML format

01/28/2019

Wilshire/Rodeo Station Monthly Look-Ahead for February
Area: Wilshire/Rodeo

This monthly notification is an outline of construction activities related to the Wilshire/Rodeo Station for the month of February 2019. 

More information about Wilshire/Rodeo Station Monthly Look-Ahead for February in HTML format

01/18/2019

Nighttime Advance Utility Relocation (AUR) on Constellation Blvd.
Area: Avenue of the Stars/Constellation

Starting Tuesday, January 22, advanced utility relocation (AUR) for AT&T will occur in Century City on Constellation Blvd., between Avenue of the Stars and Century Park East. There will be no additional lane reductions during this work. 

More information about Nighttime Advance Utility Relocation (AUR) on Constellation Blvd. in HTML format

01/17/2019

North Canon Dr. Closure
Area: Wilshire/Canon

Closure of N Canon Dr at Wilshire Bl starting early 2019 for approximately 24 months.

More information about North Canon Dr. Closure in HTML format

01/17/2019

Emergency Lane Closures on Northbound Century Park East
Area: Century Park East/Olympic

Northbound Century Park East has been reduced to one lane between Olympic Blvd. and Constellation Blvd. in order to support construction activities to secure the work site due to excess rain. 

More information about Emergency Lane Closures on Northbound Century Park East in HTML format

12/19/2018

Update: Sound Wall Installation around the Former Ace Gallery
Area: Wilshire/Beverly, Wilshire/Reeves

The design-build contractor for the Purple Line Extension project in Section 2 recently completed demolition of the former Ace Gallery at 9430 Wilshire Blvd. to prepare the construction staging area.

More information about Update: Sound Wall Installation around the Former Ace Gallery in HTML format

11/26/2018

Update: Seismic Boring Study on Wilshire Blvd.
Area: Wilshire

The Purple Line Extension Subway Project, Section 2 will resume seismic boring work in the City of Beverly Hills early-January, 2019. 

More information about Update: Seismic Boring Study on Wilshire Blvd. in HTML format

11/21/2018

Start of Utility Trench Work for Tunnel Boring Machines
Area: Constellation/Century Park East

Potholing and utility trench work on Century Park East is anticipated to start November 26* to identify and install underground utilities between 2040 Century Park East and the Launch Box on Constellation Blvd. 

More information about Start of Utility Trench Work for Tunnel Boring Machines in HTML format

11/13/2018

Postponed: Start of Utility Potholing in Beverly Hills
Area: Wilshire/Canon, Wilshire/Crescent

This work will take place on Wilshire Blvd. and S. Canon Dr. from November 13-21and includes utility trenching and potholing to investigate the soil to confirm any underground obstructions such as utilities. 

More information about Postponed: Start of Utility Potholing in Beverly Hills in HTML format

09/18/2018

Constellation Blvd. Closure at Century Park East, Beginning September 21
Area: Constellation/Century Park East

Constellation Blvd. at Century Park East will be closed to construct a launch box for the Purple Line Extension tunnel boring machines digging the twin tunnels for the underground subway through Century City.

More information about Constellation Blvd. Closure at Century Park East, Beginning September 21 in HTML format

08/28/2018

AUR Work on Constellation Bl and Avenue of the Stars
Area: Constellation Bl

AUR work

More information about AUR Work on Constellation Bl and Avenue of the Stars in HTML format

01/10/2018

Reubicación de la parada de autobus - Wilshire/Rodeo
Segment: Wilshire
Area: Wilshire/Rodeo

A partir del domingo 14 de enero, las paradas de autobús de la línea 720 del autobús de tránsito rápido, la línea 20 local del Metro y la línea 786 de Antelope Valley (ATVA) se reubicarán.

More information about Reubicación de la parada de autobus - Wilshire/Rodeo in HTML format

01/10/2018

Bus Stop Relocations - Wilshire/Rodeo
Segment: Wilshire
Area: Wilshire/Rodeo

Beginning Sunday, January 14, bus stops for Metro Rapid Bus 720, Metro Local 20, and Antelope Valley (ATVA) 786 will be relocated. Bus stops are being relocated due to on-going construction activities on Wilshire Blvd.  

More information about Bus Stop Relocations - Wilshire/Rodeo in HTML format