Start Date Notice Brief More Info

10/07/2019

Update: Wilshire Blvd. Piling Activities to Begin October 9, 2019 through July 2020
Area: Wilshire/Beverly, Wilshire/Canon

Construction activities related to piling are anticipated to begin October 9, 2019 and continue through July 2020*. 

More information about Update: Wilshire Blvd. Piling Activities to Begin October 9, 2019 through July 2020 in HTML format

10/07/2019

Purple Line Extension Community Meetings & Events
Area: Purple Line Extension

Purple Line Extension Transit Projects community meetings and events. 

More information about Purple Line Extension Community Meetings & Events in HTML format

09/26/2019

Wilshire/Rodeo Station Monthly Look-Ahead for October
Area: Wilshire/Rodeo

This monthly notification is an outline of construction activities related to the Wilshire/Rodeo Station for the month of October 2019. 

More information about Wilshire/Rodeo Station Monthly Look-Ahead for October in HTML format

09/26/2019

Century City/Constellation Station Monthly Look-Ahead for October
Area: Century City

This monthly notification is an outline of construction activities for the month of October 2019. Additional notices detailing these activities will be sent by email through the Purple Line Extension, Section 2 database.

More information about Century City/Constellation Station Monthly Look-Ahead for October in HTML format

08/23/2019

Utility Work on Avenue of the Stars and Constellation Blvd.
Area: Avenue of the Stars/Constellation

Los Angeles Department of Water and Power (LADWP) utility work will continue through Friday, August 23 and Monday, August 26 through Wednesday, August 28 on Avenue of the Stars and Constellation Blvd. from 9am to 3pm.

More information about Utility Work on Avenue of the Stars and Constellation Blvd. in HTML format

08/22/2019

Installation of Traffic Signal at Clifton Way and Crescent Dr.
Area: Clifton/Crescent

The design-build contractor for the Purple Line Extension Project Section 2 will install a 4-way traffic signal at the intersection of Clifton Way/Crescent Dr. beginning Wednesday, August 28, 2019. 

More information about Installation of Traffic Signal at Clifton Way and Crescent Dr. in HTML format

08/09/2019

North Cañon Dr. Closure
Area: Wilshire/Canon

Closure of N. Cañon Dr. at Wilshire Bl starting September 9, 2019 for approximately 24 months.

More information about North Cañon Dr. Closure in HTML format

07/16/2019

Ogden Dr. Closure
Area: Wilshire/Ogden

Concrete deliveries from the Ogden Staging Yard to the Fairfax Station are anticipated to continue through August 2019. 

More information about Ogden Dr. Closure in HTML format

07/15/2019

Weekend Utility Work on Wilshire Blvd. between El Camino Dr. and Crescent Dr.
Area: Wilshire/El Camino, Wilshire/Crescent

The design-build contractor for the Purple Line Extension Project Section 2 continues utility work on Wilshire Blvd. between El Camino Dr. and Crescent Dr. 

More information about Weekend Utility Work on Wilshire Blvd. between El Camino Dr. and Crescent Dr. in HTML format

07/12/2019

Updated: Sewer Work at Wilshire Blvd. Alley between N. Cañon Dr. and N. Crescent Dr.
Area: Wilshire/Beverly

The design-build contractor for the Purple Line Extension Project Section 2 continues sewer line replacement and relocation on Wilshire Blvd. between Beverly Dr. and Crescent Dr. Closure of the alley on the north side of Wilshire Blvd. between N. Cañon Dr. and N. Crescent Dr. and closure of the westbound curb lane on Wilshire Blvd. beginning July 18, 2019 for an estimated two weeks.* A flagger will be available at the alley to control traffic. 

More information about Updated: Sewer Work at Wilshire Blvd. Alley between N. Cañon Dr. and N. Crescent Dr. in HTML format

05/07/2019

Update: Sewer and Water Line Replacement and Relocation on Wilshire Blvd.
Area: Wilshire/Beverly, Wilshire/Crescent

The design-build contractor for the Purple Line Extension Project Section 2 will begin sewer and water line replacement and relocation on May 13, 2019 on Wilshire Blvd. between Beverly Dr. and Crescent Dr. 

More information about Update: Sewer and Water Line Replacement and Relocation on Wilshire Blvd. in HTML format

03/28/2019

Constellation Blvd. Closure at Century Park East, Beginning September 21
Area: Constellation/Century Park East

Constellation Blvd. at Century Park East will be closed to construct a launch box for the Purple Line Extension tunnel boring machines digging the twin tunnels for the underground subway through Century City.

More information about Constellation Blvd. Closure at Century Park East, Beginning September 21 in HTML format