Wilshire Blvd. and Rimpau Blvd. Work Zone

  • The work zone on the west side of the Wilshire Blvd. and Rimpau Blvd. intersection is anticipated to be in place through March 2022. Wilshire Blvd. is reduced to two lanes in each direction between June St. and Muirfield Rd.
  • Concrete and material deliveries are anticipated to continue in through April 2021.
  • Wilshire Blvd. may be intermittently reduced to a single lane in each direction to support ongoing concrete pours into the enclosure.