West Segmenet Construction Week Look-Ahead

Summary

Wilshire/Orange Grove pile prep work: Saw cutting, pot holing. 
Monday, November 7th thru Friday, November 11th – 7am-11pm

  • Orange Grove Ave. east side sidewalk closed between 8th St. and Wilshire Blvd. Northbound Orange Grove Ave. - soft closure between 8th St. and Wilshire Blvd.
  • Wilshire Blvd. south side sidewalk closed between Ogden Dr. and Orange Grove Ave.
  • Pedestrian detour signage will be installed.

Wilshire/Fairfax intersection pile prep: Pot holing, saw cutting, chipping, removal and backfill
Monday, November 7th thru Friday, November 11th, 9am-3:30pm

  • Northbound Fairfax Ave. reduced to one lane between 8th St. and Wilshire Blvd.
  • Southbound Fairfax Ave. reduced to one lane between 6th St. and Wilshire Blvd.
  • Eastbound Wilshire Blvd. reduced to one lane just west of Fairfax Ave.

Piling in the Ogden yard for the future Fairfax station portal will occur:
Monday, November 7th thru Friday, November 11th Piling work activity, 7 am-11pm. Support activities as needed, 11pm-7am 

Essentials

TIME:

  • Fairfax potholing: 7am-11pm
  • Fairfax piling: 7am-11pm
  • Support activities: 11pm-7am as needed

WHEN: Monday, November 7 – Friday, November 11

WHERE: Wilshire/Fairfax

WHAT: Potholing, Piling  

What to Expect

  • All work has received necessary permits and approvals.
  • Access for pedestrians will be maintained outside of the construction zone.
  • Access for emergency responders will be maintained.
  • Real-time information will be available at metro.net/service/advisories or 323.gometro.

Noteworthy

Construction is a dynamic process and information is subject to change without notice. 

24/7 Hotline – 213-922-6934