Skip to Content

Utility Installation: 5th/Flower

Summary

LADWP will continue utility installation on Flower St and 5th St. Work is anticipated to continue on Sunday, May 16, 2021 from 7pm to 5am and continue for approximately one week. Anticipated work hours, weather permitting, are 7pm to 5am, Monday through Friday. Saturdays and Sundays, as needed. Additional work may be scheduled at a later date. A supplemental notice will be issued once work is scheduled.

 Essentials

Thru traffic maintained. Lane reductions in place during work hours:

·      Southbound Flower St between 5th St and 6th St

·      Westbound 5th St between Flower St and Figueroa

 Construction equipment will be staged and demobilized from the site daily.  This work is being coordinated with other relocation activities in the area to minimize impacts to the community. 

 What to Expect

  • Activities include setting up traffic control, asphalt saw-cutting, excavating, installing power vault and conduits, backfilling, grinding, hauling material and supplies.
  •  Access to pedestrians will be maintained outside of the work area.