Skip to Content

Sewer Line Installation

Summary

Regional Connector Constructors (RCC) will continue the installation of a sewer line on Temple St between Alameda and Garey St. Work continues Monday, September 28, 2020 and continues for approximately five months. Anticipated work hours are Monday through Friday, 7:30 am to 3:30 pm. Saturday as needed.

 

Essentials

Activities will include set up for traffic, saw cutting, breaking up of concrete, excavating, support of excavation, sewer line installation, placing back fill material, and paving.  Closure of the south side sidewalk on Temple St during work hours. Detour: use the alternate route signage for north sidewalk. Pedestrian access will be maintained outside of the work area during work hours. 

 

What to Expect 

Thru traffic on Temple St will be maintained. Lane reductions in place on Temple St between Alameda and Garey St.