Regional Connector Constructors (RCC) will continue utility investigation and installation of piles along Temple St at Alameda.

Weekday Work: This activity is anticipated to continue Wednesday, December 15, 2020, from 7 am to 3:30 pm, and continue for approximately two months.

Saturday Work: Anticipated to continue on Saturday, December 12, 2020, from 7 am to 7 pm, and continue on Saturdays, for approximately two months. Additional work may be scheduled at a later date. A supplemental notice will be issued once work is scheduled.

 

 Essentials

Activities include saw-cutting, excavation, survey, backfill, concrete placement, and pile installation. Access to businesses and driveways will be maintained. Pedestrian crosswalks at Temple and Alameda may be restricted intermittently during work hours. Pedestrians will be detoured outside the work zone.

 

What to Expect

Weekday Work: Thru traffic maintained. Lane reduction will be in place on Temple St between Alameda and Garey St.