Fairfax Avenue Decking, February 10th

Wilshire/Fairfax Decking: What you need to know

WHAT IS DECKING

The Purple Line Extension Subway Project has been engaged in construction activities along Wilshire Bl and Fairfax Av since May 2014. Work began with advanced utility relocation (AUR), followed by major subway construction in late 2016 with pile installation. The underground piles will provide structural support for the excavation of the subway station box at Wilshire/Fairfax. The next step following piling is decking. Decking is a construction process that entails excavating the street and sidewalks, and replacing them with temporary concrete deck panels. This will allow traffic to continue to flow, while maintaining access to sidewalks and driveways as construction continues underground

In the Wilshire/Fairfax area, decking will occur on Wilshire Bl stretching from Ogden Dr, thru the Fairfax Av intersection, to San Diego Way. This work – excavating Wilshire Bl and placing steel beams and deck panels across the street – will occur over 18 weekends starting in February 2017. Sidewalk access will be maintained; however, some infrequent closures may occur depending on the nature of the work. 

QUÉ ES EL ENTABLADO | 데크 설치란

TYPICAL WEEKEND SCHEDULE

February 2017 - Spring 2017

  • Fridays 10am: 
    • Wilshire Bl (Phase 1 and Phase 3) reduced to one lane each direction
    • Fairfax Av (Phase 2) reduced to one lane in each direction
  • Fridays 8pm:
    • Full Closure of Wilshire Bl (Phase 1 and Phase 3)
    • Wilshire/Fairfax Av Intersection (Phase 2)
  • Monday 6am: Streets open

WHAT TO EXPECT

  • Thru the weekend, work will occur 24/7
  • Decking will require approximately 18 weekend closures
  • Metro bus stops may be relocated. For information changes to Metro service, please call 323.GoMetro or visit: metro.net/service/advisories/bus

WORK IS SCHEDULED IN 3 PHASES

  • Phase I: Wilshire Bl, Spaulding Av to Fairfax Av
  • Phase II: Wilshire/Fairfax Av Intersection
  • Phase III: Wilshire Bl, Fairfax Av to Crescent Heights Bl

 

WILSHIRE/FAIRFAX STATION STATS

  • 800 ft. long
  • 70 ft. wide
  • 60 ft. deep

Phase 1: Wilshire Bl, Spaulding Av to Fairfax Av (Westbound/Eastbound) 

ESSENTIALS

  • In the work zone, Wilshire Bl reduced to one lane in each direction from Spaulding Av to Fairfax Av on Fridays from 10am – 8pm
  • In the work zone, full closure of Wilshire Bl, from Spaulding Av to Fairfax Av, starting at 8pm on Fridays until Mondays at 6am

 

DETOURS

  • Westbound Wilshire: Northbound La Brea Av to Westbound 6th St to Southbound Fairfax Av to Westbound Wilshire Bl
  • Eastbound Wilshire: Northbound Fairfax Av to Eastbound 6th St to Southbound La Brea Av to Eastbound Wilshire Bl

 

ADDITIONAL LANE REDUCTIONS STARTING AT 8PM LEADING TO FULL CLOSURE

  • Westbound Wilshire: Wilshire Bl reduced at Mansfield Av
  • Eastbound Wilshire: Wilshire Bl will remain two lanes up to Fairfax Av

 

NOTE

Local access on Wilshire Bl for business and residents will be maintained. The farthest that thru traffic can travel before needing to turn is:

  • Westbound Wilshire: Wilshire Bl at Spaulding Av
  • Eastbound Wilshire: Wilshire at Fairfax Av

*Street signage will be provided

 

Phase 2: Wilshire/Fairfax Av Intersection (Westbound/Eastbound) 

ESSENTIALS:

  • In the work zone, lane reductions on Wilshire Bl and Fairfax Av will start on Fridays from 10am - 8pm
  • In the work zone, full closure of Wilshire Bl and Fairfax Av starting at 8pm on Fridays until Mondays at 6am

 

DETOURS

  • Westbound Wilshire: Westbound Wilshire Bl to Southbound La Brea Av to Westbound Olympic Bl to Northbound San Vicente Bl to Westbound Wilshire Bl
  • Eastbound Wilshire: Eastbound Wilshire Bl to Southbound La Cienega Bl to Eastbound Olympic Bl to Northbound La Brea Av to Eastbound Wilshire Bl

 

ADDITIONAL LANE REDUCTIONS STARTING AT 8PM LEADING TO FULL CLOSURE

  • Westbound Wilshire: Wilshire Bl reduced at Mansfield Av
  • Eastbound Wilshire: Wilshire Bl reduced beginning west of La Cienega Bl

 

NOTE

Local access on Wilshire Bl for business and residents will be maintained. The farthest that thru traffic can travel before needing to turn is:

  • Westbound Wilshire: Wilshire Bl at Spaulding Av
  • Eastbound Wilshire: Wilshire Bl at Crescent Heights Bl

*Street signage will be provided

 

Phase 2B: Wilshire/Fairfax Av Intersection (Southbound/Northbound)

ESSENTIALS:

  • In the work zone, lane reductions on Wilshire Bl and Fairfax Av will start on Fridays from 10am – 8pm
  • In the work zone, full closure of Wilshire Bl and Fairfax Av starting at 8pm on Fridays until Mondays at 6am

 

DETOURS

  • Southbound Fairfax: Southbound Fairfax Av to Eastbound 6th St to Southbound La Brea Av to Westbound Olympic Bl to Southbound Fairfax Av
  • Northbound Fairfax: Northbound Fairfax Av to Eastbound Olympic Bl to Northbound La Brea Av to Westbound 6th St to Northbound Fairfax Av

 

ADDITIONAL LANE REDUCTIONS STARTING AT 8PM LEADING TO FULL CLOSURE

  • Southbound Fairfax: Fairfax Av reduced at at Maryland Dr
  • Northbound Fairfax: Fairfax Av reduced beginning south of Olympic Bl

 

NOTE

Local access on Fairfax Av for business and residents will be maintained. The farthest that thru traffic can travel before needing to turn is:

  • Southbound Fairfax: Intersection of Fairfax Av and 6th St
  • Northbound Fairfax: Intersection of Fairfax Av and 8th St

*Street signage will be provided

 

Phase 3: Wilshire Bl, Fairfax Av to Crescent Heights Bl (Westbound/Eastbound)

ESSENTIALS:

  • In the work zone, Wilshire Bl reduced to one lane in each direction from Fairfax Av to Crescent Heights Bl on Fridays from 10am – 8pm
  • In the work zone, full closure of Wilshire Bl, from Fairfax Av to Crescent Heights Bl start at 8pm on Fridays until Mondays at 6am

 

DETOURS

  • Westbound Wilshire: Westbound Wilshire Bl to Southbound Fairfax Av to Westbound San Vicente Bl to Westbound Wilshire Bl
  • Eastbound Wilshire: Eastbound Wilshire Bl to Southbound La Cienega Bl to Eastbound Olympic Bl to Northbound La Brea Av to Eastbound Wilshire Bl

 

ADDITIONAL LANE REDUCTIONS STARTING AT 8PM LEADING TO FULL CLOSURE

  • Westbound Wilshire: Wilshire Bl reduced at Ogden Dr
  • Eastbound Wilshire: Wilshire Bl reduced beginning west of La Cienega Bl

 

NOTE

Local access on Wilshire Bl for business and residents will be maintained. The farthest that thru traffic can travel before needing to turn is:

  • Westbound Wilshire: Wilshire Bl at Fairfax Av
  • Eastbound Wilshire: Wilshire at Crescent Heights Bl

*Street signage will be provided

*Construction is a dynamic process and information is subject to change without notice. Detour routes are subject to change at the discretion of the Department of Transportation.