East + West Segment Construction Week Look-Ahead

East Segment Summary

Wilshire/Rossmore jet grouting, saw cutting, and pot holing 
Monday, November 28 – Friday, December 2, 9am - 3:30pm

  • Eastbound Wilshire Blvd. reduced to one lane between Rossmore Ave. and Lucerne Ave.
  • Westbound Wilshire Blvd. reduced to one lane between Lucerne Ave. and Rossmore Ave. 

La Brea Station excavation and geotechnical instrumentation installation at Wilshire/Orange Dr 
Monday, November 28 – Friday, December 2, 7am - 11pm

  • South side of Orange Dr. fully closed at Wilshire Blvd. Local access maintained from 8th St.
  • Tuesday, November 29 – 9pm - 1am – excavation equipment placement underneath the deck. Wilshire Blvd. will be reduced to one lane in each direction between La Brea Ave. and Mansfield Ave.

Station excavation will continue in the La Brea staging yards through August of 2017.

Essentials

TIME:

  • Station excavation: 7am - 11pm
  • Dewatering maintenance: 9am - 3:30pm
  • Equipment placement underneath the deck: 9pm - 1am 

WHEN: Monday, November 28 – Friday, December 2 
WHERE: Wilshire/La Brea

West Segment Summary

Wilshire/Orange Grove pile preparation: saw cutting and pot holing
Monday, November 28 thru Friday, December 2, 7am - 11pm 

  • Orange Grove Ave. east side sidewalk closed between 8th St. and Wilshire Blvd. Signed pedestrian detour will be installed.
  • Orange Grove Ave. closed to thru traffic at Wilshire Blvd. Access from 8th St. maintained.
  • Wilshire Blvd. south side sidewalk closed between Ogden Dr. and Orange Grove Ave. Signed pedestrian detour will be installed.

South side of Wilshire pile preparation behind K-rail: pot holing, saw cutting, chipping, removal and backfill
Monday, November 28 thru Friday, December 2, 9am - 3:30pm 

  • Southside Wilshire Blvd. sidewalk closed between Orange Grove Ave. and Ogden Dr. Signed pedestrian detour will be installed.

Essentials

TIME:

  • Wilshire Blvd./Orange Grove Ave. pile preparation: 7am - 11pm  
  • Pile preparation behind K-rail: 9am - 3:30pm 

WHEN: Monday, November 28 – Friday, December 2 
WHERE: Wilshire/Fairfax 
WHAT: Piling preparation

Metro Access

Metro bus stops may be relocated or line could be impacted. For information changes to Metro service, please call 323.GoMetro or visit:

Noteworthy

  • All work has received necessary permits and approvals.
  • Access for pedestrians will be maintained outside of the construction zone.
  • Access for emergency responders will be maintained.
  • Construction is a dynamic process and information is subject to change without notice. 
  • 24/7 Hotline: 213-922-6934