West Segment Construction Look-Ahead

Summary

Wilshire/Orange Grove pile preparation: Saw cutting, potholing work
Monday, October 31-Friday, November 4 – 7am - 11pm

  • Orange Grove Ave. east side sidewalk closed between 8th St. and Wilshire Blvd. Northbound Orange Grove St. soft closure between 8th St. and Wilshire Blvd.
  • Signed pedestrian detour will be installed.
  • Wilshire Blvd. south side sidewalk closed between Ogden Dr. and Orange Grove Ave.
  • Signed pedestrian detour will be installed.

Wilshire/Fairfax intersection pile prep: Potholing, saw cutting, removal and backfill
Monday, October 31-Friday, November 4 – 8pm - 11pm

  • Northbound Fairfax Ave. reduced to one lane between 8th St. and Wilshire Blvd.
  • Southbound Fairfax Ave. reduced to one lane between 6th St. and Wilshire Blvd.
  • Eastbound Wilshire Blvd. reduced to one lane just west of Fairfax Ave.

Piling work in the Ogden yard for the future station portal.
Monday, October 31 – Friday, November 4.

Piling work on Wilshire/Fairfax 7 am - 11pm.
Support activities as needed 11pm - 7am.  

Essentials

TIME: Fairfax potholing: 7am - 11pm
         Fairfax piling: 7am - 11pm – support activities 11pm - 7am as needed

WHEN: Monday, October 31st – Friday, November 4th

WHERE: Wilshire/Fairfax

WHAT: Potholing, Piling  

What to Expect

  • All work has received necessary permits and approvals.
  • Access for pedestrians will be maintained outside of the construction zone.
  • Access for emergency responders will be maintained.
  • Real-time information will be available at metro.net/service/advisories or 323.gometro.

Noteworthy

Construction is a dynamic process and information is subject to change without notice.

24/7 Construction Hotline: 213-922-6934