Beverly Hills Update: AM/PM Utility Relocation Work at Wilshire/La Cienega

Last Updated

3/23/2017

Summary

Advanced utility relocation work will continue during the week and over the weekend along the north side of Wilshire Blvd. and on La Cienega Blvd. north of Wilshire thru April 3rd. 

Work will occur along the north side of Wilshire Blvd. between La Cienega Blvd. and Le Doux Rd. and on La Cienega Blvd. just north of Wilshire Blvd. This work will consist of accessing the vaults for cable pulling activities.

See intermittent lane reductions and sidewalk impacts below:

Wilshire Blvd.: One lane will remain open westbound between La Cienega Blvd and Le Doux Rd.

La Cienega Blvd.: Reduced to 2 lanes north of Wilshire Blvd. to Clifton Way, with a partial sidewalk closure adjacent to the La Cienega staging yard.

Essentials

Work hours and dates*: 

  • Friday, 3/24 at 11pm to Saturday, 3/25 at 7am
  • Saturday, 3/25 at 7am-6pm and Sunday, 3/26 from Midnight-6am 
  • Sunday, 3/26 at 8pm to Monday, 3/27 at 7am
  • Monday, 3/27 at 8pm to Tuesday 3/28 at 7am
  • Tuesday, 3/28 at 8pm to Wednesday 3/29 at 7am
  • Wednesday, 3/29 at 10pm to Thursday, 3/30 at 7am
  • Thursday, 3/30 at 8pm to Friday, 3/31 at 7am
  • Friday, 3/31 at Midnight to Saturday, 4/1 at 7am
  • Saturday, 4/1 at 7am-8pm and 8pm to Sunday, 4/2 at 7am
  • Sunday, 4/2 at 7am-8pm and 8pm to Monday, 4/3 at 7am

*Pending City of Beverly Hills approval

Noteworthy

  • Construction within project staging yards is 24-hours/day. 
  • All work has received necessary permits and approvals.
  • Access for pedestrians will be maintained outside of the construction zone.
  • Access for emergency responders will be maintained.
  • Construction is a dynamic process and information is subject to change without notice.
  • 24/7 Hotline: 213.922.6934

Contact Us

Phone: 213.922.6934
Email | Facebook | Twitter

Sign up to receive constructions notices via email

Safety First

  • Please review our construction safety tips
  • Access for emergency responders will be maintained
  • Construction is a dynamic process and information is subject to change without notice

Metro Access

Metro bus stops for 720/20 have been relocated to Wilshire Blvd./Stanley Ave. and Wilshire Blvd./La Jolla Ave. Metro buses will post stop relocations and announce relocations and detours to riders.

For information changes to Metro service, please call 323.GoMetro or visit: https://www.metro.net/service/advisories/

More About Metro

Eat Shop Play

  Support businesses located along the project alignment!  Eat, Shop, Play locally during construction.  For all the details, visit metro.net/eatshopplay

Business Interruption Fund

  Metro's Business Interruption Fund (BIF) provides financial assistance to qualifying small “mom and pop” businesses directly impacted by construction; learn more by visiting metro.net/bif.  To apply, visit Metro’s program administrator, Pacific Coast Regional Small Business Development Corporation (PCR)

Doing Business With Metro 

  Metro works with small businesses throughout Los Angeles County! Would you like to be one of our vendors? Visit business.metro.net for more details!
Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero