Request for Temporary Full Closure of Wilshire Blvd. During COVID-19 Restrictions

Summary

Metro and the City of Beverly Hills have been exploring alternatives to help expedite the construction of the Wilshire/Rodeo Station. A full closure of Wilshire Blvd. between Crescent Dr. and Beverly Dr. was identified as a potential option to help work progress during the statewide pandemic health restrictions.

The full closure would allow the contractor to utilize additional equipment, which would help expedite the completion of piling on the south side of Wilshire Blvd. as well as decking.

Metro anticipates that this closure could be in place from 1-3 months; however, upon request of the City, the contractor will restore the street to the current configuration.

Implementation of the Wilshire Blvd. temporary full closure could result in a potential time savings of 6 months, when these activities would have otherwise continued through March 2021 under normal conditions.

Proposed Work: 

  • Temporary full closure of Wilshire Blvd. between Crescent Dr. and Beverly Dr. for piling on the south side of the street and as well as decking.
    • Piling work hours would remain the same (8am – 9pm) for drilling activities, (9pm – 11pm) for non-drilling activities.
    • S. Cañon Dr. and Reeves Dr. will remain closed at Wilshire Blvd. for pile installations for the duration of the full Wilshire Blvd. closure.
    • During decking, work will occur during night hours per the MOA.
  • Closures of the Wilshire Blvd./Beverly Dr. intersection for piling across Beverly Dr.
  • Additionally, Metro has requested an exemption from the current peak hour hauling restrictions of  7am – 9am and   4pm – 7pm.

Essentials

These items will be going to City Council on March 31, 2020 for their consideration and approval. If you have any questions or comments related to this item, you can e-mail the City at purpleline@beverlyhills.org or call 310-703-1385.

For additional information about the upcoming Beverly Hills Council meeting please go to BeverlyHills.org

As part of the State, County, and applicable City orders specific to the COVID-19 response, Metro construction activities are currently included as “Essential” activities.  Therefore, construction activities are continuing as permitted by the local jurisdiction.

Metro Access

Our construction may have relocated your bus stop, or changed your route. For information changes to Metro service, please call 323.GoMetro or visit: https://www.metro.net/service/advisories/

Noteworthy

  • Construction within project staging yards is 24-hours/day. 
  • All work has received necessary permits and approvals.
  • Access for pedestrians will be maintained outside of the construction zone.
  • Access for emergency responders will be maintained.
  • Construction is a dynamic process and information is subject to change without notice.
  • 24/7 Hotline: 213.922.6934

Contact Us

Phone: 213.922.6934
Email | Facebook | Twitter

Sign up to receive construction notices via email

Click here to go to the Purple Line Extension Project homepage

Safety First

_____________________________________________________________________________________

More About Metro

Eat Shop Play

Support businesses located along the project alignment!  Eat, Shop, Play locally during construction.  For all the details, visit metro.net/eatshopplay

Business Interruption Fund

Metro's Business Interruption Fund (BIF) provides financial assistance to qualifying small “mom and pop” businesses directly impacted by construction; learn more by visiting metro.net/bif.  To apply, visit Metro’s program administrator, Pacific Coast Regional Small Business Development Corporation (PCR)

Doing Business with Metro 

Metro works with small businesses throughout Los Angeles County! Would you like to be one of our vendors? Visit business.metro.net for more details!