Lane Closures for Wilshire Blvd./Beverly Dr. Intersection Piling

Summary

As part of the pile installation, the design-builder will install 27 piles across Beverly Dr. on the north side of Wilshire Blvd. beginning January 29, 2020 through April 2020. Pile installation will require partial lane and crosswalk closures 7 days a week. Work will occur in two stages with implementation of one stage at a time to allow for 2 way traffic flow on one side of Beverly Dr. 

During work hours, Beverly Dr. will be reduced to one lane northbound and southbound from Dayton Way to Charleville Blvd. Throughout piling, left turns are not permitted onto Beverly Dr. or Crescent Dr. from Wilshire Blvd. Work hours within the intersection are weekdays from 9am to 4pm and weekends from 7am to 10pm. 

Essentials

WHERE: 

  • North and west crosswalks at Wilshire Blvd./Beverly Dr. will be closed during work hours. A pedestrian detour will be provided.
  • Partial lane closure on Beverly Dr. at Wilshire Blvd. One lane will be maintained northbound and southbound during work hours.

WHEN: 

  • January 29, 2020 through April 2020*
  • Work hours: Weekdays: 9am – 4pm and Weekends: 7am – 10pm (non-drilling activities after 8pm)

ACCESS:

  • North and west crosswalks at Wilshire Blvd./Beverly Dr. will be closed during work hours. A pedestrian detour will be provided.
  • Partial lane closures will be in place during work hours. One lane will be maintained northbound and southbound on Beverly Dr. from Dayton Wy. to Charleville Blvd.

*Work has received necessary permits and approvals or are pending approval by the City of Beverly Hills. Additional construction notices will be distributed with further details prior to the start of major activities. 

Metro Access

Metro bus stops may be relocated or lines will be impacted. For information changes to Metro service, please call 323.GoMetro or visit: https://www.metro.net/service/advisories/

Noteworthy

  • All work has received necessary permits and approvals.
  • Access for pedestrians will be maintained outside of the construction zone.
  • Access for emergency responders will be maintained.
  • Construction is a dynamic process and information is subject to change without notice.
  • 24/7 Hotline: 213.922.6934

Contact Us

Phone: 213.922.6934
Email | Facebook | Twitter

Safety First

  • Please review our construction safety tips
  • Access for emergency responders will be maintained
  • Construction is a dynamic process and information is subject to change without notice

_____________________________________________________________________________________

More About Metro

Eat Shop Play

Support businesses located along the project alignment!  Eat, Shop, Play locally during construction.  For all the details, visit metro.net/eatshopplay

Business Interruption Fund

Metro's Business Interruption Fund (BIF) provides financial assistance to qualifying small “mom and pop” businesses directly impacted by construction; learn more by visiting metro.net/bif.  To apply, visit Metro’s program administrator, Pacific Coast Regional Small Business Development Corporation (PCR)

Doing Business with Metro 

Metro works with small businesses throughout Los Angeles County! Would you like to be one of our vendors? Visit business.metro.net for more details!

·         orth and west crosswalks at Wilshire Blvd./Beverly Dr. will closed during work hours. Pedestrian detour will be provided.

Partial lane closures will be in place during work hours. One lane will be maintained northbound and southbound on Beverly Dr. from Dayton Wy. to Charleville Blvd.