Skip to Content

Concrete and Rebar Deliveries at Wilshire/La Cienega

Summary

Concrete and rebar deliveries to the Wilshire/La Cienega Station Box are anticipated to begin in September. Work hours are anticipated to increase as excavation work concludes underneath Wilshire Blvd. The following traffic control and work hours are anticipated to be in place. 

September 2019 – October 2019*

  • Between 7am and 4pm, Wilshire Blvd. between San Vicente Blvd. and La Cienega Blvd. will be intermittently reduced to two lanes in each direction.
  • Between 10pm and 7am, Wilshire Blvd. between San Vicente Blvd. and La Cienega Blvd. will be intermittently reduced to one lane in each direction.
  • Left turns from Wilshire Blvd. to side streets may be restricted during these lane restrictions.
  • Metro and STS have requested to begin night work hours at 8pm instead of 10pm. This will allow many of the noisier activities to be completed earlier.
  • Closures are anticipated to be in place 2 to 3 days per week. 

November 2019 – March 2020*

  • Between 7am and 4pm, Wilshire Blvd. between San Vicente Blvd. and La Cienega Blvd. will be intermittently reduced to two lanes in each direction.
  • Between 10pm and 7am, Wilshire Blvd. between San Vicente Blvd. and La Cienega Blvd. will be intermittently reduced to one lane in each direction.
  • Left turns from Wilshire Blvd. to side streets may be restricted during these lane restrictions.
  • Metro and STS have requested to begin night work hours at 8pm instead of 10pm. This will allow many of the noisier activities to be completed earlier.
  • Closures are anticipated to be in place 5 to 7 days per week 

* Pending City of Beverly Hills Approval. Continued coordination will take place with the businesses in this work zone. 

Metro Access

Our construction may have relocated your bus stop, or changed your route. For information changes to Metro service, please call 323.GoMetro or visit: https://www.metro.net/service/advisories/

Noteworthy

  • Construction within project staging yards is 24-hours/day. 
  • All work has received necessary permits and approvals.
  • Access for pedestrians will be maintained outside of the construction zone.
  • Access for emergency responders will be maintained.
  • Construction is a dynamic process and information is subject to change without notice.
  • 24/7 Hotline: 213.922.6934

Contact Us

Phone: 213.922.6934
Email | Facebook | Twitter

Sign up to receive construction notices via email

Click here to go to the Purple Line Extension Project homepage

Safety First

_____________________________________________________________________________________

More About Metro

Eat Shop Play

Support businesses located along the project alignment!  Eat, Shop, Play locally during construction.  For all the details, visit metro.net/eatshopplay

Business Interruption Fund

Metro's Business Interruption Fund (BIF) provides financial assistance to qualifying small “mom and pop” businesses directly impacted by construction; learn more by visiting metro.net/bif.  To apply, visit Metro’s program administrator, Pacific Coast Regional Small Business Development Corporation (PCR)

Doing Business with Metro 

Metro works with small businesses throughout Los Angeles County! Would you like to be one of our vendors? Visit business.metro.net for more details!

Advertisement