Summary
As part of Metro’s Crenshaw/LAX Transit Project, Walsh-Shea Corridor Constructors (WSCC) will be working on roadway paving for the grade crossings along Crenshaw Bl. This work will require street closures for eastbound and westbound traffic on Crenshaw Bl between Slauson Av and 50th St. Closures will be implemented one intersection at a time.
Essentials
WHAT: Street closure
WHEN: Starting 6 am Thursday, July 30, 2020.
WHERE: At Crenshaw Bl and 50th and 57th Streets
What to Expect
Closures of Crenshaw Bl (rail-crossing) intersections
- Closure at 54th St
6 am on Thursday, July 30, 2020, until 6 am on Monday, August 3, 2020. - Closure at 52nd St
6 am on Tuesday, August 4, 2020, until 3 pm on Wednesday, August 5, 2020. - Closure at Slauson Av
Postponed to a later time - Closure at 50th St
6 am Friday, August 14, 2020, through 6 am Monday, August 17, 2020. - Closure at 57th St
6 am Tuesday, August 18, 2020, through 3 pm Wednesday, August 19, 2020. - Left turn movements will be restricted during each street closure.