Full Street Closure of Victoria Ave between Slauson Ave and 57th St

Summary

As part of Metro’s Crenshaw/LAX Transit Project, Walsh-Shea Corridor Constructors (WSCC) will be working on the restoration of the roadway, which will include demolition, excavation, backfill, and paving of Slauson Ave. This work will require the full closure of Victoria Ave between Slauson Ave and 57th St, for one weekend starting at 6 am Friday, May 22, 2020, through 6 am Monday, May 25, 2020.

Essentials

WHAT: Full street closure
WHEN: Starting 6am Friday, May 22, 2020 through 6am Monday, May 25, 2020. Weather permitting.
WHERE: Slauson Ave and Victoria Ave
DURATION: One Weekend

What to Expect

Lane closures adjacent to the construction activity on Slauson Av between 11th Ave and Brynhurst Ave

Westbound detour:

  • Westbound Slauson Ave
  • Northbound on Brynhurst Ave
  • Eastbound on 57th St

Eastbound Detour:

  • Eastbound on Slauson Ave
  • Northbound on Crenshaw Bl
  • Westbound on 57th St

Access to Victoria Ave will be maintained at 57th St.