Pile installation at Duco Yard

Summary

RCC continues pile installation along northbound Alameda St within the Duco yard.

Pile installation is anticipated to begin as early as Tuesday, February 25, 2020, and continue for approximately six weeks.

Anticipated work hours are Monday through Friday from 9 am to 3:30 pm.

Additional work may be scheduled at a later date. A supplemental notice will be issued once work is scheduled.

Essentials

Activities include; saw cutting, excavation, surveying of existing underground utilities, pile installation and backfilling.

What to Expect

  • Pile installation will be conducted within the Duco Yard with no impacts to traffic.
  • L (Gold) Line service to remain in place during this activity.
  • These efforts are necessary to build the Alameda tunnel box that will allow the L (Gold) Line to have a west and a south terminus. 