Lowering of equipment below deck at 1st St/Alameda St intersection

Summary

Regional Connector Constructors (RCC) will be lifting deck panels to lower equipment below deck at the 1st St and Alameda intersection.

Work is anticipated to begin on Saturday, November 23, 2019. Work hours, weather permitting, are from 8 am to 4 pm for one day only.

Essentials

Activities include: removing deck panels, mobilizing equipment and materials below deck, and installation of a manhole.

The crosswalk at the 1st St and Alameda intersection may be restricted intermittently during work hours. Detour: use the alternate route signage.

Pedestrian access will be maintained outside of the work zone.

What to Expect

Alameda St

  • Thru traffic will be maintained on northbound Alameda.
  • A directional closure will be in place on southbound Alameda between 1st St and 2nd St. Detour: make a right on 1st St, left on Central Av, left on 2nd St, back onto Alameda.

1st St

  • Thru traffic will be maintained on westbound 1st St.
  • A directional closure will be in place on eastbound 1st St between Central Av and Alameda. Detour: make a right on Central Av, left on 2nd St, left on Alameda, back onto 1st St.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook