Deck Panel Install on 1st St between Alameda St and Rose St

Update

May 1, 2019: This activity has been rescheduled to begin as early as Friday, May 3, 2019.


Summary

Regional Connector Constructors (RCC) will be installing deck panels on eastbound 1st St, between Alameda St and Rose St.

Work is anticipated to begin as early as Friday, May 3, 2019, and conclude Saturday, May 4. Anticipated work hours, weather permitting, are from 5 am to 9 am on Friday and 8 am to 3:30 pm on Saturday.

Essentials

Activities include deck panel installation and yard maintenance. Work will extend outside the k-rail on 1st St.

Pedestrian access will be maintained outside of the work area during work hours. Sound mitigations will be in place.

What to Expect

Thru traffic and local access on 1st St will be maintained.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook