Third party work: SoCalGas utility relocation

Update

May 17, 2019: The duration of this work has been extended to Tuesday, May 21.


Summary

SoCalGas will perform utility relocation on Alameda St between 1st St and Commercial St. Work is anticipated to begin on Monday, April 22, 2019, and continue through May 21.

Work hours, weather permitting, are Monday through Friday from 9 am to 3:30 pm.

Additional work may be scheduled at a later date. A supplemental notice will be issued once work is scheduled.

Essentials

Activities will include; setting up traffic control, saw cut, grind, excavation, laying of pipe, backfill, paving, and moving supplies in and out of the work zone.

Access to all adjacent businesses will be maintained.

Pedestrian access will be maintained outside of the work zone.

What to Expect

Thru traffic will be maintained with lane reductions in place on northbound and southbound Alameda St between 1st St and Commercial St.

This work is being coordinated with other relocation activities in the area.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook