Skip to Content

Deck Panel Removal and Excavation

Update

Thursday, March 14: Schedule for March 16 planned lane closures on 6th St and Flower St now available.


Summary

Regional Connector Constructors will remove deck panels and excavate on at the intersection of 6th St and Flower.

Work is scheduled to begin Saturday, March 16, 2019, and last for one day. Anticipated work hours, weather permitting, are 7 am to 5 pm.

Essentials

Activities include traffic control set up, equipment mobilization, deck panel removal and replacement, and excavation.

Access to pedestrian walkways, driveways, and nearby businesses will be maintained

What to Expect

Between 8 and 10 am, expect the following lane closures:

  • Lane closures on the north side of 6th St, between Figueroa and Flower St, and the west side of Flower St, between 5th St and 6th St, with work occurring at the northwest corner of the intersection.

Between 10 am and 3 pm, expect the following lane closures:

  • Southbound Flower St will be reduced to a single thu-lane between 5th St and Wilshire Bl, and a left turn lane onto eastbound 6th St.
  • The right turn lane from eastbound 6th St onto southbound Flower St will be closed with right turns restricted.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Advertisement