Installation of ground monitoring device on 2nd St and Spring St

Update

October 11, 2018: Duration of work extended to Friday, October 12, from 9:30 to 11:30 am.


Summary

Regional Connector Constructors (RCC) will be installing a ground monitoring device just south of the 2nd St and Spring St intersection.

Work is anticipated to begin Thursday, October 11, 2018 for approximately one hour from 9:30 am to 10:30 am, as well as on October 12, from 9:30 to 11:30 am.

Essentials

Activities include geotechnical instrument installation. Geotechnical instrumentation is needed to monitor the on-going underground work during construction.

Access to crosswalks, nearby driveways, and businesses will be maintained.

What to expect

A lane reduction will be implemented during work hours. A flagger and traffic truck will be directing traffic around the installation location.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero