Restoration Paving 7th Street

Summary

Regional Connector Constructors (RCC) will perform restoration paving on 7th Street between Figueroa and Flower St.

Work is anticipated to begin Wednesday September 19th and continue for three days.

Anticipated work hours, weather permitting, are Wednesday through Friday, 7 am to
3:30 pm.

Essentials

Activities include steel plate removal, grinding, and paving.

What to Expect

Thru lanes will be maintained on 7th St and Flower St with no detours needed.