Skip to Content

Concrete placement on Flower St

Update

Concrete placement scheduled for the following dates, weather permitting:

  • Friday, October 23
  • Tuesday, October 27
  • Friday, October 30
  • Friday, November 6
  • Friday, November 13

Set up scheduled to starts as early as 5 am, unless otherwise noted. Sound mitigations will be in place. Dates are subject to change.


Summary

Regional Connector Constructors (RCC) will place concrete slabs in to continue the construction of the tunnel box structure.

Anticipated work hours, weather permitting, are 3 am to 3 pm.

Essentials

Activities include concrete pumping and placement within the construction work site.

What to expect

Work will be maintained within the current worksite, behind k-rail closures with no additional street closures or lane reductions needed.

Trucks will be staged on southbound Flower St and enter the site south at the intersection of 4th St and Flower St, with a flagger on-site to assist.