Sidewalk improvements on east side of Flower St

Update

September 21, 2018: Updated "What to expect."

September 20, 2018: Saturday work start times now beginning at 7 am.


Summary

The Regional Connector Constructors (RCC) will perform sidewalk improvements on the east side of Flower St, between 5th St and 6th St.

Work is anticipated to begin Monday, September 17, 2018, and last for approximately two weeks. Anticipated work hours, weather permitting, are 9 am to 3:30 pm, Monday through Friday, and 7 am to 6 pm on Saturday.

Essentials

Activities include sawcutting, grinding, excavation, dirt removal, drain installation, ADA ramp improvements and paving.

What to Expect

  • There will be intermittent sidewalk closures along the east side of Flower St with diversions in place for pedestrians.
  • Work will require a partial closure of the Westlawn Garage and California Club north driveway, with flaggers on site to assist traffic.
  • The Standard, Paragon Parking, and California Club south driveway will be closed completely Saturday, September 22.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero