Geotechnical Installation on 2nd St

Update

July 20, 2018: No weekend work. Work will resume on Monday, July 23, 2018 until Thursday July 26, 2018, from 9 am to 3 pm, weather permitting.


Summary

Regional Connector Constructors (RCC) will be installing geotechnical instrumentation on 2nd St between Spring St. and Main St.

Work is anticipated to begin Thursday, July 19, 2018 and continue through July 26. Daytime work hours, weather permitting, from 5 am to 3 pm.

Essentials

Activities include: drilling, installation of instrumentation, and back fill.

Sound mitigations will be in place during work hours. Pedestrian, business, and local access will be maintained.

What to Expect

Day time traffic restrictions:

  • No detours will occur.
  • Work will start at 2nd St and Spring St. and move east.
  • A rolling road closure will take place on 2nd St in each lane throughout the day to complete instruments in all traffic lanes.
  • A traffic control truck and flagger will be present to direct traffic around the work zone.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero