Skip to Content
Search

Geotechnical Installation on 2nd St from Main to Spring St

Summary

Regional Connector Constructors (RCC) will be installing geotechnical instrumentation on 2nd St from Main to Spring St.

Work is anticipated to begin Wednesday, June 13, and continue to Friday, June 15, 2018. Day time work hours, weather permitting, are from 7 am to 3:30 pm, Wednesday through Friday. Night time work hours, weather permitting, 9pm to 5am, Thursday only.

Essentials

Activities include: drilling, installation of instrumentation, and back fill.

Sound mitigations will be in place during work hours. Pedestrian, business, and local access will be maintained.

What to Expect

Day time traffic restrictions

  • Westbound lane reduction on 2nd St. between Spring and Main.
  • The parking lane on eastbound 2nd St will be restricted.
  • Lane reduction on northbound Spring.

Thursday night traffic restrictions

  • Westbound and eastbound directional closures will be in place at separate times.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero