1st and Central Concrete Placement

Concrete placement scheduled for the following dates*, weather permitting, starting as early as 6 am. Sound mitigations will be in place.

  • Thursday, July 16
  • Monday, July 20
  • Tuesday, July 21
  • Wednesday, July 22
  • Thursday, July 23
  • Monday, July 27
  • Tuesday, July 28
  • Friday, July 31
  • Monday, August 3
  • Tuesday, August 4
  • Wednesday, August 5

*Concrete delivery and placement times will vary. Dates subject to change.


Summary

Regional Connector Constructors (RCC) will be placing concrete within the future Little Tokyo/Arts District Station.

Anticipated work hours, weather permitting, are 4 am to 6 pm, Monday through Friday and 8 am to 3 pm on Saturdays.

Concrete delivery and placement times will vary throughout the anticipated work hours.

Español  日本語   한국어 

Essentials

Activities include concrete delivery, pumping, and placement within the station limits.

Sound mitigations will be in place during work hours. Pedestrian, business, and local access will be maintained.

What to Expect

Concrete trucks will enter the project site from Alameda Street and stage within the yard.

Work will be behind the current k-rail. No additional closures will be required.