Concrete Placement at the Historic Broadway Station

Update:

Thursday, May 17: Concrete placement now scheduled through May 31, 2018.


Summary

Regional Connector Constructors (RCC) will begin placing concrete slabs within the Historic Broadway Station.

Work activity is anticipated to begin Monday, May 7, for one week. Anticipated work hours, weather permitting, are 7 am to 12 am.

Essentials

Activities include concrete delivery, pumping, and placement. Concrete delivery and placement times will vary throughout the anticipated work hours. Sound mitigations will be in place.

What to Expect

  • Work will be behind current k-rail with no additional closures needed.
  • Concrete trucks entering the project site through Spring St will be staged within the construction site.

Program Notes