Concrete Placement at the Historic Broadway Station

Update

July 15, 2019: Concrete placement scheduled for the following dates*, weather permitting, starting as early as 7 am. Sound mitigations will be in place.

  • Wednesday, July 17
  • Thursday, July 18

*Concrete delivery and placement times will vary. Dates subject to change.


Summary

Regional Connector Constructors (RCC) will begin placing concrete slabs within the Historic Broadway Station.

Work activity is anticipated to begin Monday, May 7, and will continue until 2020. Anticipated work hours, weather permitting, are 7 am to 12 am, on varying days.

Essentials

Activities include concrete delivery, pumping, and placement. Concrete delivery and placement times will vary throughout the anticipated work hours. Sound mitigations will be in place.

What to Expect

  • Work will be behind current k-rail with no additional closures needed.
  • Concrete trucks entering the project site through Spring St will be staged within the construction site.