Concrete Placement at the Historic Broadway Station

Update

June 25, 2018: Updated new concrete placement schedule, through 2020.


Summary

Regional Connector Constructors (RCC) will place concrete slabs within the Historic Broadway station.

Work activity is anticipated to begin on Monday, May 7, 2018, until 2020. Anticipated work hours, weather permitting, are from 8 am to 3 pm.

Essentials

Activities include: concrete pumping and placement within the station. First hour will be used for set up. Sound mitigations will be in place.

What to Expect

Work will be behind current k-rail with no additional closures needed.