Concrete Placement at the Historic Broadway Station

Update

Friday, May 4: Work hours for Wednesday, May 19, 2018, will begin at 4 am, for one day only.


Summary

Regional Connector Constructors (RCC) will place concrete slabs within the Historic Broadway station.

Work activity is anticipated to take place on Saturday, March 10, for one day. Anticipated work hours, weather permitting, are from 8 am to 3 pm.

Essentials

Activities include: concrete pumping and placement within the station. First hour will be used for set up. Sound mitigations will be in place.

What to Expect

Work will be behind current k-rail with no additional closures needed.