4th St Sewer Activities between Figueroa St and Flower St

Update

Wednesday, December 20: The duration of this work has been extended through February 2018.

Wednesday, December 13: Start date for this work rescheduled to Friday, December 15.


Summary

Regional Connector Constructors (RCC) will perform utility surveys on 4th St between Figueroa St and Flower St.

Work is anticipated begin Friday, December 15, and continue through February 2018. Anticipated work hours, weather permitting, are from 9 am to 3 pm.

Essentials

Work will include surveying the interior of a sewer manhole and installing stop locks into a sewer manhole.

Pedestrian access will be maintained.

What to Expect

Lane reductions will be in place on Figueroa St between 3rd St and 6th St. There will also be a lane reduction on Flower St between 3rd St and 5th St.

Northbound Flower St will be closed at 4th St.

  • Traffic exiting the J2 Garage to turn left on Flower St.
  • All traffic on eastbound lower 4th St will have to turn right on Flower St.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero