Power Relocation Activities on Flower St between 6th St and Wilshire Bl

Summary

Regional Connector Constructors (RCC) will continue power relocation efforts on Flower St between 6th St and Wilshire Bl.

Work is anticipated to continue Monday, November 20, and continue for approximately six weeks.

Anticipated work hours, weather permitting, are Monday to Friday 9 am to 3:30 pm and 7 pm to 5 am; Saturdays and Sundays, as needed, from 8 am to 6 pm. Sound mitigation measures will be in place during working hours.

Essentials

Activities include saw cutting, grinding, pavement removal, excavation, backfill, and paving. Access to all adjacent buildings will be maintained at all times. Pedestrian access will be maintained at all times.

What to Expect

Flower St

  • Lane reductions from 5th to Wilshire

6th St

  • Lane reductions from Figueroa St to Hope St.
  • Right turns from eastbound 6th St to southbound Flower St will be restricted intermittently. 
  • Left turns from southbound Flower St to eastbound 6th St will be restricted intermittently.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero