Regional Connector Constructors (RCC) will be installing geotechnical instrumentation near the intersection of 4th St and Flower St.
Work will begin on Wednesday, October 4, 2017, and continue for 3 days. Anticipated work hours are from 9 am to 3:30 pm.
Essentials
Geotechnical instrumentation is needed to monitor the underground work during construction.
Pedestrian access will not be impacted during this activity.
What to Expect
During work hours there will be a lane reduction of southbound Flower St traffic approaching 4th St.
Two southbound lanes will be maintained on Flower St at all times.
Access to the World Trade Center Parking Garage will be maintained during work hours.
Program Notes