Utility Investigation and Piling at the Southeast Corner of 5th St/Flower St

Summary

Regional Connector Constructors (RCC) will continue utility investigation activities and pile installation at the southeast corner of the 5th St and Flower St intersection.

Work is anticipated to continue Monday, September 18, for approximately two months.

Anticipated work hours:

  • Monday to Friday: 7 am to 3:30 pm and 3:30 pm to midnight
  • Saturdays: 7 am to 9 pm
  • Sundays (as needed): 7 am to 9 pm

Thru traffic will be maintained at all times on southbound Flower St.

Essentials

The east side pedestrian sidewalk on Flower St between 5th St and midblock crosswalk will be restricted during work hours. Access will be maintained outside of the work zone.

Access to driveways will be maintained at all times.

What to Expect

Lane reductions will be in place on Flower St between 5th St and 6th St, along with lane reductions on westbound 5th St between Olive and Flower St.

Left turns from westbound 5th St to southbound Flower St will be maintained.

Detour:

  • Pedestrians will be detoured to the west side sidewalk on Flower St between 5th St. and the midblock crosswalk.
  • Crosswalks at 5th St/Flower St and the 6th St/Flower St intersections will be open at all times.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero