Sawcutting Activities at the 5th/Flower Intersection

Update

Friday, September 8: The duration of this activity has been extended to September 15.


Summary

Regional Connector Constructors (RCC) will perform sawcutting and grinding activities at the 5th/Flower intersection in support of ongoing deck installation efforts.

Work is anticipated to begin Tuesday, September 5, and will continue until September 15. Anticipated work hours are from 7 pm to 9 pm, Monday through Friday.

Lane reductions will be in place at the following locations:

  • Flower St between 4th St and 5th St
  • 5th St between Grand Av and Figueroa St.

Thru traffic on Flower St and 5th St will be maintained during this activity.

Essentials

Activities include sawcutting, grinding and street restoration.

What to Expect

Flower St will be intermittently reduced to one lane at the 5th/Flower intersection during this activity. Crosswalk restrictions will be in place at the 5th/Flower intersection during this activity. Only one crosswalk will be closed at a time.

Pedestrian access will be maintained outside of the work zone.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero