Power Duct Bank Installation on Flower St. between 5th St. and 6th St.

Update

Friday, August 11: This activity has been rescheduled to a new date in the future yet to be determined.


Summary

LADWP Power will begin night work in support of power duct bank installation efforts on Flower St, between 5th St and 6th St. Work starts Monday, August 14 and will continue nightly between the hours of 7 p.m. and 4 a.m. for approximately two weeks.

Flower St. between 5th St. and 6th St. will be reduced to one thru lane. Thru traffic on Flower St. will be maintained.

Essentials

Activities include; sawcutting, excavation, conduit installation, backfilling, grinding and hauling. Pedestrian access will be maintained outside of the work area.

What to Expect

Sawcutting and grinding activities will take place between the hours of 7 p.m. and 9 p.m. Sound mitigation measures will be in place during working hours.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero