Sound Wall Installation on Flower St Eastside Pedestrian Sidewalk

Update

Friday, August 18: The duration of this activity has been extended to August 26.

Friday, August 11: The duration of this activity has been extended to August 12.


Summary

Regional Connector Constructors will install a sound wall on the eastside sidewalk on Flower St between 4th St and 5th St. This will require a full closure of the pedestrian sidewalk.

Work is anticipated to begin Saturday, July 22, and continue through August. Anticipated work hours will be 8 am to 6 pm, Saturdays only.

Essentials

Pedestrian access will be maintained. Access to driveways will be maintained at all times.

What to Expect

No traffic closures needed.

Sidewalk access will be restricted on the eastside of Flower Street between 4th St. and the 5th/Flower St intersection. Driveway access will be maintained.

Detour
Pedestrians will be detoured to the west side sidewalk on Flower St between 4th St. and 5th St. Crosswalks at the 5th/Flower intersection and the 4th/Flower intersection will be open at all times.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero