Sound Wall Installation on Flower St Eastside Pedestrian Sidewalk

Update

Friday, September 1: Pedestrian detour information has been updated.

Tuesday, August 29: This activity has been rescheduled to begin September 6.

Friday, August 25: This activity has been rescheduled to begin September 9.

Friday, August 18: The duration of this activity has been extended to August 26.

Friday, August 11: The duration of this activity has been extended to August 12.


Summary

Regional Connector Constructors will install a sound wall on the east side sidewalk on Flower St between 4th St and 5th St.

Work is anticipated to begin Wednesday, September 6, and continue for three days. Anticipated work hours will be 8 am to 5 pm..

The east side sidewalk of Flower St between 4th and 5th St will be restricted during this activity

Essentials

Activities include drilling, installation of steel beams, backfilling, installing sound wall panels and hanging noise blankets. Access to driveways will be maintained at all times.

What to Expect

No vehicular traffic closures needed.

Sidewalk access will be restricted on the eastside of Flower Street between 4th St. and the 5th/Flower St intersection. Driveway access will be maintained.

Detour

  • Pedestrians will be detoured to the west side sidewalk on Flower St between 4th St. and 5th St. Crosswalks at the 5th/Flower intersection and the 4th/Flower intersection will be open at all times. 
  • J2 Garage and Citigroup use 4th St pedestrian bridge.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero