Geotechnical Instrumentation Installation on Flower St between 5th and 6th St

Update

Friday, September 8: The duration of this activity has been extended to September 15.

Friday, August 11: The duration of this activity has been extended to August 31.

Friday, August 4: The duration of this activity has been extended to August 18.


Summary

Regional Connector Constructors (RCC) will be installing geotechnical instrumentation on the east side of Flower St between 5th St and 6th St.

Work will begin on Monday, July 17, 2017 and continue until September 15 with the exception of Monday July 24 through Wednesday July 26. Anticipated work hours are 7 am to 6 pm.

Access to nearby businesses will be maintained.

Essentials

At least three crosswalks will remain open at all times. Parking garage access will be maintained at all times.

Geotechnical instrumentation is needed to monitor the underground work during construction.

What to Expect

Work will take place behind the existing k-rail traffic closure on the east side of Flower St No additional traffic control is necessary for this work. Access to pedestrians will be maintained outside of the work area.