Weekend Closure for Cut and Cover Activities Continues on Flower St. between 4th St. and 5th St.

Summary

Regional Connector Constructors (RCC) will continue cut and cover activities on Flower St. between 4th St. and 5th St. This activity requires thru traffic be restricted on Flower St. from 3rd St. to 5th St.

Work will begin at 7 pm on Friday May 5, 2017 and will remain in place through 5 am Monday, May 8, 2017.

The following activities will take place during the closure: saw cutting, roadway removal, beam installation, protection of utilities and temporary deck panels will be installed.

Essentials

Traffic will be allowed through Lower 4th St from Figueroa St. to Flower St. to access local businesses.

Local access to businesses will be maintained during the closure. Pedestrian access will be maintained outside the construction area.

Flaggers will be onsite to facilitate access.
Please follow the posted detour signs.

What to Expect

  • Lane reductions on westbound 5th St. between Grand Ave. and Flower St.
  • Access to all parking garages will be maintained.
  • Access to Bonaventure parking garage and drop-off will be from lower 4th St.

Detours:

  • The primary detour will route traffic from Hope St. to Grand Ave. via 1st St. then back to Flower St. via 5th St. 
  • The Secondary detour will route traffic from Flower St. to Beaudry St. Via 3rd St. then back to Flower St. via 6th St.

Geotech Instrument Installation on 5th St, between Flower St and Figueroa St

Summary

Regional Connector Constructors (RCC) will be installing geotechnical instrumentation on westbound 5th St. between Flower St. and Figueroa St.

Work will take place on Saturday, January 14, for one day. Anticipated work hours, weather permitting, are from 8 a.m. to 6 p.m.

Access to nearby businesses will be maintained.

Essentials

At least three crosswalks will remain open at all times. Parking garage access will be maintained at all times.

Geotechnical instrumentation is needed to monitor the underground work during construction.

What to Expect

Lane reductions will be in place on westbound 5th St. between Flower St. and Figueroa St. Access to pedestrians will be maintained outside of the work area.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero