Storm Drain Installation on 2nd St. between Broadway and Spring St.

Update

Friday, April 28: Updated scope of construction activities.

Summary

Regional Connector Constructors (RCC) will be performing storm drain installation on 2nd St. between Spring St. and Broadway.

Work is anticipated to begin Monday, May 8, 2017 and continue for three weeks. Anticipated work hours will be between 7 pm to 5 am, Monday through Saturday.

This activity will require a full closure of 2nd St between Broadway and Spring St. Traffic control will be setup nightly and reopen traffic on a daily basis.

Essentials

Pedestrian access will be maintained outside of the work area during work hours.

Activities will include fine grading for pipe bed, laying pipe, removing and replacing deck panels.

What to Expect

2nd St. between Spring St. and Broadway will be restricted.

Left turns from southbound Broadway to eastbound 2nd St. and right turns from southbound Spring St. to west bound 2nd St. will be restricted during the work hours.

Westbound 2nd St. Detour

  • Left on Spring St., right on 3rd St., right on Broadway and back on westbound 2nd St.

Eastbound 2nd St. Detour

  • Left on Broadway, right on 1st St., right on Spring St., and back on eastbound 2nd St.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero