Construction Activities at the 2nd/Hope Yard

Summary

Regional Connector Constructors (RCC) will continue construction activities at the future 2nd/Hope Station in order to prepare for the arrival of the tunnel boring machine.

Work is anticipated to continue Monday, April 10, for approximately two months. Anticipated work hours, weather permitting, are:

  • 7 am to 3:30 pm 
  • Monday through Friday.

Essentials

Activities include installation of tunnel eye, site grading and hauling of material. Access to pedestrians will be maintained outside of the work area.

What to Expect

Work will take place within current traffic closure. No additional traffic closures needed.