Geotechnical Instrumentation Installation on Flower St. between 3rd St. and 4th St

Update

Friday, April 14: Duration of work extended to April 21.

Summary

Regional Connector Constructors (RCC) will be installing geotechnical instrumentation on northbound Flower St. between 3rd St. and 4th St.

Work will begin on Monday, April 10 and continue for 5 days. Anticipated work hours, weather permitting are from 9 am to 3:30 pm, Monday through Friday.

Access to nearby driveways and businesses will be maintained.

Essentials

All crosswalks will remain open. Parking garage access will be maintained at all times.

Geotechnical instrumentation is needed to monitor the underground work during construction.

What to Expect

Northbound Flower St. will be closed during work hours. Access to the Bank of America driveway will be maintained at all times.

Left turns from southbound Flower into the J-2 garage may be restricted intermittently during the duration of work. Please use 4th St. to access the parking garage during this time.

Access to pedestrians will be maintained outside of the work area.

Program Notes

Eat, Shop, Play Local

Website | Upcoming Events | Twitter | Facebook

Was this information useful?

Share this page on
Advertisement
Close Search Window

Search metro.net, The Source, and El Pasajero